Call for tenders' details

Please be informed that the deadline for dispatching tenders has been extended by 10 working days, i.e., the new deadline for receipt of tenders is 05/11/2014 (14:00 CET). Consequently, the new deadline for questions is 27/10/2014 and the opening of tenders will be organized on 11/11/2014 at 14:00 CET. All dates indicated in e-Tendering will be updated as soon as the corrigendum in the contract notice will be published in the Official Journal.
Title:
Internet and landline telephone services.
Contracting authority:
EUROJUST
TED publication date:
05/09/2014
Time limit for receipt of tenders:
05/11/2014
Status:
Closed
Show filter parameters

Results per page: 10 | 25 | 50 119 Questions found, displaying 41 to 50.[First/Prev] 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12 [Next/Last]
# Question Answer Last publication date Status
79
53: Contractor can agree to this clause provided that it is adjusted as follows: “One-off license fees [...]
No, the Article III.1.5.3 will not be amended.
16/10/2014
78
52: Contractor can agree to this clause provided that it is adjusted as follows: “Purchases shall be [...]
No, the Article III.1.5.2 will not be amended.
16/10/2014
77
51: Contractor cannot accept to be liable for payment of liquidated damages in the event an invoice is [...]
No, this phrase of the Article II.1.5.1 will not be deleted.
16/10/2014
76
50: Contractor is of the opinion that Eurojust’s requirement for price adjustments (except to extent [...]
No, the Article III.1.4 will not be deleted. Please note that according to the terms of the precedence [...]
16/10/2014
75
49: Parties agree on fixed prices as a result of this tender procedure. It should not be Parties’ intention [...]
No, the Article III.1.3.1 will not be deleted.
16/10/2014
74
48: Eurojust shall merely receive a non-exclusive, non-transferable, revocable right, not subject to [...]
No, the Article III.1.2 will not be deleted.
16/10/2014
73
47: Contractor cannot agree to the fact that it is not entitled to claim compensation on account of suspension [...]
No, the Article II.19 will not be amended.
16/10/2014
72
46: This article is not acceptable for Contractor. Merely to the extent such use, distribution, etc. [...]
No, the Article II.18 will not be amended.
16/10/2014
71
45: Contractor cannot agree to the condition that Eurojust shall be entitled to claim any damage suffered [...]
No, the Article II.12.4 will not be amended.
16/10/2014
70
44: Contractor can accept this clause provided that the clause is adjusted as follows: ”where the Contractor [...]
No, the Article II.12.1 (f) will not be amended.
16/10/2014