Call for tenders' details

Title:
ICT Infrastructure Services — Provision of Operation and Support Services of the...
Contracting authority:
European Parliament, DG Innovation and Technological support (ITEC)
TED publication date:
18/02/2020
Time limit for receipt of tenders:
16/06/2020
Status:
Closed
Show filter parameters

Results per page: 10 | 25 | 50 151 Questions found, displaying 131 to 140.[First/Prev] 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16 [Next/Last]
# Question Answer Last publication date Status
22
Concerning SLA 321/322/421/422 (Provisioning Time) As those SLA’s are strongly dependent of the architecture [...]
Any delay due to external circumstances and not imputable to the contractor will not be taken into account [...]
10/03/2020
21
The ratio is calculated per service (Design-Transition-Operations-Core Team): quid the experts Core Team [...]
We assume you are referring to KPI 133. A cumulative effect is indeed possible and the EP may be entitled [...]
10/03/2020
20
Concerning SLA111/121/131/133 ratio of staff turnover. Can you confirm that these indicators are calculated [...]
The KPIs will be calculated monthly, taking into account the previous 12 months for the turn-over calculation [...]
10/03/2020
19
In the hypotheses that EP would receive only two responses (as happened with ITOMS13 with a similar SLA [...]
The Financial Regulation, especially Point 23 of Annex I, will be applied.
10/03/2020
18
Based on the answer (06/03/2020) regarding the question 10 about Contract termination, could the European [...]
The European Parliament confirms its answer from 6.3.2020 stating that the contractor cannot terminate [...]
10/03/2020
17
Our understanding is that tenderers can submit letters or certificates already signed by the purchaser [...]
Form T2 is a certificate of delivery to be filled in and signed by the tenderer's client having executed [...]
09/03/2020
16
In the ITOMS19 tender specifications, section “I.15.1.1.2 Technical Offer Lot 2”, page 20, the Parliament [...]
Thank you for raising this topic. After verification of the matter that you mention, we confirm that [...]
09/03/2020
15
With regard to the “Form 3.2.A - Information Sheet concerning groups of economic operators”, we have [...]
We have corrected the title and uploaded a new version of the Tender specifications document.
09/03/2020
14
With regard to "Form 3.2.b AGREEMENT/POWER OF ATTORNEY TO BE COMPLETED IN CASE OF GROUP/TEMPORARY ASSOCIATION [...]
We have corrected the reference and uploaded a new version of the Tender specifications document.
09/03/2020
13
Our understanding is that the power of signature must be submitted by the sole tenderer or the group [...]
Your understanding is correct.
09/03/2020