22
|
Is it possible to replace the evidences of the exclusion criteria (i.e. extract from the judicial record [...]
|
Please repeat the question and provide the website address of the Public Procurement Office quoted in [...]
|
12/03/2020
|
|
21
|
Is it required for proposed subcontractor which meet some selection criteria by its technical and proffesional [...]
|
No, each subcontractors shall provide “complete and sign Declaration on Honour, by a person authorised [...]
|
11/03/2020
|
|
20
|
Will you approve certificate IQBBA CFLBA as equivalent to the following requirement "Holds Certified [...]
|
Yes. For the purpose of this tender Frontex will accept IQBBA CFLBA as an equivalent of “Certified Business [...]
|
11/03/2020
|
|
19
|
The Business/System Analyst profile requires 2 certifications, namely CBAP and OCUP. We consider that [...]
|
Frontex expects to from the tenderer to propose person that fulfils both requirements as described in [...]
|
11/03/2020
|
|
18
|
Will you agree to modify the requirements for Business/System Analyst profile and approve to submit 2 [...]
|
Frontex expects to from the tenderer to propose person that fulfils both requirements as described in [...]
|
11/03/2020
|
|
17
|
The table of the Named Personnel Available for the contract should be sign: a) by the person who are [...]
|
As indicated in the chapter 5.3.3.1. Personnel capacity of Annex I under Evidence required: The form [...]
|
11/03/2020
|
|
16
|
The certification required for the IT Security Specialist is CISSP or CISA or equivalent. Those certifications [...]
|
Frontex will treat ISO 27001 Lead Auditor certificate as an equivalent to CISA.
|
06/03/2020
|
|
15
|
Whom is this about "extracting from the judicial record" (chapter 2.2.). Is this about the responsible [...]
|
The Candidate (in the case of joint candidatures, each candidate, including members of a consortium) [...]
|
04/03/2020
|
|
14
|
Will you accept references project delivered by subcontractor to meet minimum reference requirements [...]
|
Yes (as indicated in the chapter 5.5 of Annex I) but only for the Minimum Mandatory Requirements of the [...]
|
03/03/2020
|
|
13
|
According to " Successful implementation of these projects must be evidenced by reference letters issued [...]
|
No, as the acceptance protocols often does not provide the information about the “successful implementation [...]
|
03/03/2020
|
|