32
Information from the Contracting authority - Invitation Letter
Please note that the document ' Invitation letter', is now available in version 3.
03/06/2020
Answered
31
Public opening - Information from the Contracting authority
Subject to the developments related to COVID-19 pandemic and respective public health measures, the contracting [...]
03/06/2020
Answered
30
can you please clarify if the cost of the development work for the web service-based product access and [...]
The costs for the operation of the Web service-based product access and dissemination system should be [...]
26/05/2020
Answered
29
With reference to your clarification #23 to the question about Partner and subcontractor participation [...]
It must preliminarily be underlined, that the assessment will be carried out by the Evaluation Committee [...]
25/05/2020
Answered
28
Dear Sir/Madam, With reference still to the current situation in Europe due to the Covid-19 spread, restrictions [...]
Please note that the tender deadline has already been extended twice, first on 20 March 2020 for an additional [...]
25/05/2020
Answered
27
Dear Sir/Madam, with reference to the ongoing emergency status related to the Covid-19 spread, increased [...]
Please note that the tender deadline has already been extended twice, first on 20 March 2020 for an additional [...]
25/05/2020
Answered
26
The invitation letter sets out the requirements for submitting hand-signed documents as having to be [...]
Considering the current exceptional circumstances, the contracting authority agrees to temporarily accept [...]
22/05/2020
Answered
25
Are cost eligible for travel and subsistence for trips with a duration of several weeks to partners/ [...]
Travel and subsistence costs are only eligible and foreseen for short-term trips such as kick-off meetings [...]
18/05/2020
Answered
24
To decide whether the flooding event is correctly detected the comparison (overlap) of detected (i.e. [...]
As indicated in the previous answer, thematic accuracy is computed based on a comparison of the flood [...]
14/05/2020
Answered
23
Could you please clarify if different departments of a single institute of research, with a unique PIC [...]
As long as point 10.1 of the Technical specifications Part 1: administrative annex is respected, all [...]
14/05/2020
Answered