33. Do EMSA BCF has access conditions to take the racks completed or need to be in parts (ex: weight [...]
|
The current EMSA BCF hosting site has the access conditions to move the complete racks.
|
05/05/2020
|
|
46
|
32. The move includes cables?
|
Yes all cables should be moved and re-installed to be re-used in the new hosting center.
|
05/05/2020
|
|
45
|
31. The move of the systems/equipment is just in one wave or EMSA need more than one wave to do the move [...]
|
The move shall be performed in as less time as possible in order to minimise the risk for EMSA of being [...]
|
05/05/2020
|
|
44
|
30. In any circumstances the move includes moving all the systems/equipment but not the rack?
|
Racks shall be moved together with the other equipment, and shall be re-installed to be re-used in the [...]
|
05/05/2020
|
|
43
|
29. The system/equipment in the origin site has all the cables (energy, networking, etc.) tagged or is [...]
|
It is part of the service to tag it.
|
05/05/2020
|
|
42
|
28. Is it possible to refer the validity of the contract of this systems/equipment and the entity that [...]
|
After the award of the contract, a kick off meeting will be held to review the plan for the move, and [...]
|
05/05/2020
|
|
41
|
27. It’s possible to have Serial Number of each system/equipment in scope?
|
After the award of the contract, a kick off meeting will be held to review the plan for the move, and [...]
|
05/05/2020
|
|
40
|
26. What is the scope of EMSA team in this process?
|
EMSA Team will assist at the beginning with the shutdown phase (remotely), and then it will assist again [...]
|
05/05/2020
|
|
39
|
25. It is possible to have remote access to the systems/equipment located in EMSA BCF through EMSA DC [...]
|
Yes – after the contract award.
|
05/05/2020
|
|
38
|
24. We assume that EMSA will guaranty data recovery mechanisms (backups) and have operational recovery [...]
|
Yes
|
05/05/2020
|
|
37
|
23. We assume that no contingency plan or equipment will be needed besides the insurance policy for the [...]
|
The plan for the move will be assessed based on how it handles possible risks for EMSA during the transportation [...]
|
05/05/2020
|
|
36
|
22. After the moving and physically install system/equipment in the new EMSA BCF they will be power on [...]
|
Yes data re-syncronisation, functional and application tests will be executed by EMSA Team.
|
05/05/2020
|
|
35
|
21. All IP addressing will be the same in the EMSA BCF data center? There’s no need for system/equipment [...]
|
Yes – addressing will stay the same, hence no need for reconfiguration.
|
05/05/2020
|
|
34
|
20. No new equipment will be added in new EMSA BCF data center?
|
No new equipment will be added previously and during the move.
|
05/05/2020
|
|
33
|
19. Each system/ equipment will maintain its original rack position?
|
Yes
|
05/05/2020
|
|
32
|
18. Should we presume that the move will occur in single phase?
|
Yes
|
05/05/2020
|
|
31
|
17. All system/ equipment in EMSA BCF datacentre are independent and maybe shutdown?
|
Yes
|
05/05/2020
|
|
30
|
Thus, under the terms and for the purposes of the provisions of article 21º of the DIRECTIVE 2014/24/ [...]
|
Please refer to answer provided to part I.
|
05/05/2020
|
|
29
|
In this regard, the Law No. 26/2016 of August 22, expressly states that “A third party only has the right [...]
|
Please refer to answer provided to part I.
|
05/05/2020
|
|
28
|
Paragraph 1 of article 66 of the CCP refers that “for reasons of commercial, industrial, military or [...]
|
Please refer to answer provided to part I.
|
05/05/2020
|
|
27
|
The article 21º of the DIRECTIVE 2014/24/EU OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL of 26 February [...]
|
Please refer to answer provided to part I.
|
05/05/2020
|
|
26
|
MEO – SERVIÇOS DE COMUNICAÇÕES E MULTIMÉDIA, S.A., hereinafter also referred to as “MEO”, a public limited [...]
|
"As a general obligation stemming from the Treaty on the Functioning of the European Union and the Charter [...]
|
05/05/2020
|
|
25
|
The line to connect EMSA BCF and EMSA DC, could be a L3 line (IP or MPLS) or is required to be a L2 connection [...]
|
Line can be L3.
|
05/05/2020
|
|
24
|
On the Internet Connectivity - when filling the 5Gbps solution, the price should be the total amount [...]
|
Price shall be the total amount for the 5Gbps solution. Please note that all prices in the table are [...]
|
05/05/2020
|
|
23
|
Can all documents, that are to be uploaded by the tenderer, be digitally signed? including the ones where [...]
|
"According to Section 3 of Appendix I e-Submission Guidelines attached to the Tender Specifications, [...]
|
05/05/2020
|
|