17
|
Section 4.4.6 of the tender specification says that the signed submission report (if hand-signed) should [...]
|
a) The address is correct. b) The call reference should preferably be added on the envelope but it is [...]
|
22/06/2020
|
|
16
|
Regarding Task 3, D3.2: How many infographics would need to be prepared for each of the SDG’s, and does [...]
|
Tenderers are free to propose the most suitable number of infographics for each SDG as well as to advise [...]
|
15/06/2020
|
|
15
|
Regarding Task 3, D.3.1.: how many key indicators does EUROSTAT want to be selected to improve communication [...]
|
Tenderers are free to propose the most suitable number of key indicators for each SDG.
|
15/06/2020
|
|
14
|
Regarding Task 3, D.3.2: Does EUROSTAT require that infographics be delivered in some specific format [...]
|
Eurostat requires the source files for all infographics
|
15/06/2020
|
|
13
|
Regarding Task 3, D3.2: On what communication platforms (social media, reports etc.) does Eurostat plan [...]
|
Eurostat reserves the right to determine the means of dissemination of the infographics
|
15/06/2020
|
|
12
|
Regarding task 3: “Non-experts” are defined as the target group. Do “non-experts” mean the general public [...]
|
“Non-experts” in this context mean the general public.
|
11/06/2020
|
|
11
|
We have a question relating to the expression „impacts of specific activities” which is used in the context [...]
|
Your understanding is correct. “Specific activities” refer to any sort of policy measure or state intervention [...]
|
11/06/2020
|
|
10
|
In Deliverable D3.1 the "identification of key indicators at the EU level" is requested. In this context [...]
|
The identification of key indicators is not limited to the Eurostat set but can also refer to other indicators [...]
|
11/06/2020
|
|
9
|
Could you clarify how the two contracts would be divided in two lots? Including in terms of: a. Need [...]
|
This call for tenders is not divided in lots. In accordance with point 2.5 of the tender specifications [...]
|
10/06/2020
|
|
8
|
In the perspective of COVID-19, would it be possible to reconsider the necessity of posting the original [...]
|
Documentation must be submitted as indicated in Section 4 “information on the tender procedure” of the [...]
|
10/06/2020
|
|
7
|
Dear EUROSTAT Team, Since the COVID-19 pandemic is currently leading to severe alterations in the ways [...]
|
The call for tender has been published on 30 April 2020, with a deadline for submission of 22 June 2020 [...]
|
03/06/2020
|
|
6
|
Dear Sir/Madam, in the document library, the document "List of annexes" mentions ANNEX 7 Draft contract [...]
|
Annex 7 "Draft contract" has been published in the Document library
|
29/05/2020
|
|
5
|
The Annexes to the Tender Specifications include a template for the Financial Tender, but not for the [...]
|
There is any guidance on the outline, format, structure, length or style of the Technical Tender.
|
29/05/2020
|
|
4
|
Dear EUROSTAT Team, reference is made to the scopes to be considered for Task 1 (spillover) and Task [...]
|
The Eurostat SDG monitoring report focuses on progress in the EU context. Therefore, the analysis of [...]
|
28/05/2020
|
|
3
|
In the tender it is specified that “The total volume of the work for the entire contract period is estimated [...]
|
The indicated values are correct. The estimated number of man-days covers different profiles with different [...]
|
26/05/2020
|
|
2
|
For the e-submission drafting of a new tender is it possible for more than one person, from separate [...]
|
Invitation to tender letter: Point 1. “Submission of tenders” Tenders must be submitted exclusively via [...]
|
20/05/2020
|
|
1
|
Is it ok in a joint tender for only the leader of the group to be registered with a PIC number - or do [...]
|
Section 4, point 4.3.1 of the tender specifications: “In order to submit a tender using e-Submission, [...]
|
20/05/2020
|
|