63
|
We would kindly ask you to clarify, whether the services within LOT4 can in certain cases as well include [...]
|
As described in detail on p. 26 of the Tender Specifications, the local transport is part of Lot 3.
|
05/08/2020
|
|
62
|
In connection to the reply no. 57, please can you clarify whether the payment of subsistence allowances [...]
|
No, it is not applicable for the participants of the events. Question57
|
05/08/2020
|
|
61
|
Is it allowed to repeat the Projects that fulfill Criterion T1 for LOT 3 also for criterion T2 in Lot [...]
|
The Lots are independent on each other and the tenderer can submit tenders for more than one lot as mentioned [...]
|
05/08/2020
|
|
60
|
Can you please tell us what type of banner is wanted for each event (outside / inside, size, type)?
|
There is no specific description of the banner you are requesting.
|
05/08/2020
|
|
59
|
How many pages should the programmes (flyers? brochures?) for the events have? Which format should they [...]
|
Please see the description in the Annex 6.1 Scenarios Case studies of the Tender Specifications and the [...]
|
05/08/2020
|
|
58
|
Aprox. how many participants will be attending each event?
|
Please see the description in the Annex 6.1 Scenarios Case studies of the Tender Specifications and the [...]
|
05/08/2020
|
|
57
|
Please could you clarify whether the payment of subsistence allowances is forecasted under LOT4, or LOT3 [...]
|
Subject to prior agreement from ELA, only those travel and subsistence expenses for Contractor’s staff [...]
|
03/08/2020
|
|
56
|
What exactly is the required experience in terms of the 6 events? For Lot 4 only the travel arrangements [...]
|
Yes, as described on p. 57 of the Tender specifications, the tenderer must prove experience in travel [...]
|
03/08/2020
|
|
55
|
In your reply #38 you stated that "all services for CS must be calculated". Anyway, not all services [...]
|
In CS Lot 3, all Prices per Unit in EUR must be calculated with the same amounts as in Table Lot 3. Moreover [...]
|
03/08/2020
|
|
54
|
In response to Question 37, criterion T2: - Can you please confirm that in order to demonstrate specific [...]
|
- Yes, list of projects worked on by proposed team members can be demonstrated in CVs or annexed to CV [...]
|
30/07/2020
|
|