73
|
Can we bring freelancers and declare them as subcontractors? If so, what do they have to provide?
|
Yes you can work with freelancers and declare them as subcontractors. By filling in the form available [...]
|
08/04/2021
|
|
72
|
For lot 2, it is assumed that the hosting of the necessary IT infrastructure (HW and SW) will be provided [...]
|
The hosting, monitoring and support of IT hardware and software will not be part of the tasks of the [...]
|
31/03/2021
|
|
71
|
Can you please confirm if we have to create a profile on the eSubmission for subcontractors that do not [...]
|
As explained under section 2.4.2 of the tender specifications ‘Subcontractors’, only subcontractors on [...]
|
30/03/2021
|
|
70
|
Our understanding is that if we bring a company as subcontractor, which helps the group of tenderers [...]
|
Indeed, as explained under section 2.4.2 of the tender specifications ‘Subcontractors’, Annex 5.1 should [...]
|
30/03/2021
|
|
69
|
For lot 2, Criterion T1 (p.39). Does the reference have to explicitly encompass the production of cards [...]
|
The ten projects that the tenderer must present as evidence of technical and professional capacity ought [...]
|
30/03/2021
|
|
68
|
May we confirm that: 1.) subcontractors for whom we do not rely on for selection criteria or for more [...]
|
Indeed, as explained under section 2.4.2 of the tender specifications ‘Subcontractors’, only subcontractors [...]
|
30/03/2021
|
|
67
|
Can you confirm that if and Entity on whose capacities the tenderer relies to fulfil the selection criteria [...]
|
Indeed, as explained under section 2.4.2 of the tender specifications ‘Subcontractors’, Annex 5.1 should [...]
|
30/03/2021
|
|
66
|
Can you confirm that if a subcontractor will have less than 10% of the contract volume and the tender [...]
|
Indeed, as explained under section 2.4.2 (Subcontracting) of the tender specifications, only subcontractors [...]
|
30/03/2021
|
|
65
|
The activities and services specified in the tender require diverse competencies on the part of the tenderers [...]
|
The Contracting Authority has decided to grant tenderers an additional two weeks for the submission of [...]
|
19/03/2021
|
|
64
|
Do you have an indicative distribution of the contract % of the total contract volume devoted per profile [...]
|
Please refer to Question63
|
18/03/2021
|
|