50
|
In document Annex + 6a). 2 Lot 2 in the accessory chapter, a box concerning the entry exit ramps for [...]
|
We have uploaded a new version of the Annex 1.2 Technical specifications LOT 2, of the Annex 6a).2 "Technical [...]
|
16/10/2020
|
|
49
|
In document Annex + 6a). 3 Lot 3 in the accessory chapter, a box concerning the entry exit ramps for [...]
|
Indeed, the mention of "models 1 to 6" is a mistake. Ramp measurements have been corrected. In addition [...]
|
16/10/2020
|
|
3
|
Le prix de la maintenance ne peut-il pas être globalisé pour l’ensemble du lot afin d’éviter les redondances [...]
|
The contracting authority will order the models it requires as and when needed over the course of the [...]
|
15/10/2020
|
|
9
|
Le prix du transport et de la livraison est-il inclus ?
|
The prices quoted must be flat-rate prices, meaning that they must include in particular transport, delivery [...]
|
15/10/2020
|
|
10
|
Les lignes de prix des rampes (Lignes 11 à 18) ne précisent pas quelle rampe correspond à quel modèle [...]
|
We require a flat-rate price by ramp length (lines 11 to 18), whatever the tunnel model.
|
15/10/2020
|
|
48
|
If we submit for all 3 lots, would 1 technical proposal covering all lots, although separately explained [...]
|
As specified in point 4.2 « Content of the tender » of the tender specifications: “Tenderers wishing [...]
|
15/10/2020
|
|
34
|
ANNEXE 6a) 1, 2, 3 BORDEREAU DE CONFORMITE TECHNIQUE LOTS 1, 2, 3 : - Portiques détecteurs de métal ( [...]
|
Yes, the annail update is mandatory. Critical and / or security updates affecting the software must be [...]
|
14/10/2020
|
|
45
|
There is still no case to input the unit price for Model 1 and Model 2 X ray tunnel in the financial [...]
|
You cannot split the x-ray and the tray return system, depending of lengths of the tray the price should [...]
|
14/10/2020
|
|
47
|
What does this mean? Conditions for opening tenders (date) 19/10/2020 11:00? In an earlier answer you've [...]
|
The deadline to submit tenders is extended to the 23 October 2020 16:00 instead of the the 16 October [...]
|
14/10/2020
|
|
46
|
Considering the numerous questions and answers, could you please, give 2 more weeks to submit a tender [...]
|
A corrigendum to the contract notice is about to be published. The deadline to submit a tender is postponed [...]
|
13/10/2020
|
|