17
|
Regarding the proposed draft service contract, could please confirm that the following amendments can[...]
|
This is an open tender procedure and no amendments can be negotiated. As specified in the Invitation [...]
|
05/02/2021
|
|
|
16
|
Could you please clarify which ‘products’ are to go through the approval process (outline, draft, final[...]
|
Everything that is produced under the project, including the platform, the handbook and the digital maturity[...]
|
05/02/2021
|
|
|
15
|
Is there any page limit for the technical offer? Is there any format to follow to submit the technical[...]
|
Section 4 of the tender specifications defines the form and content of the tender submission. For the[...]
|
04/02/2021
|
|
|
14
|
Does the evidence have to be provided by one person or can the experience be demonstrated as a combined[...]
|
5 years of experience for the project manager and 5 years of experience for the knowledge manager requested[...]
|
28/01/2021
|
|
|
13
|
Criterion P1 – Project Manager: The 5 years experience in project management in projects of a similar[...]
|
The tenderer, either as a single provider, or a consortium of providers must nominate one Project Manager[...]
|
27/01/2021
|
|
|
12
|
Pleace clarifies what is the minimum number of people trained? p. 15 "(and at least 300 participants [...]
|
The minimum number of people to be trained is 300 as mentioned on page 15 of the tender specification[...]
|
26/01/2021
|
|
|
11
|
- Clarification is needed of the specific tasks that a knowledge manager must develop throughout the [...]
|
Knowledge management is the process of creating, sharing, using and managing the knowledge and information[...]
|
26/01/2021
|
|
|
10
|
- Clarification is needed on who is responsible for the selection of enterprises to which the surveys[...]
|
The tasks under WP1, 2 and 3 have to be performed by the Contractor. In particular, the Contractor will[...]
|
25/01/2021
|
|
|
9
|
- Regarding the T4 requirement, clarification is needed whether there are 10 trainings in total in 3 [...]
|
Regarding the criterion T4, the tenderer must provide references for at least 10 (on-site/practical, [...]
|
25/01/2021
|
|
|
8
|
- Please confirm that online training courses could be plan for the development of WP2
|
Online trainings are only permitted as alternative due to the sanitary crisis. As mentioned in section[...]
|
22/01/2021
|
|