19
|
Our understanding is that the content of the declaration on honour (ch 3.1 of Annex 1.1) already contains [...]
|
The Declaration of Honour should be signed and provided as reference to the answer to question 3.1 of [...]
|
30/04/2015
|
|
18
|
Annex 2 – On page 24, in the paragraph dedicated to “A Business Continuity is declared on the contractor [...]
|
If the Business Continuity Plan of the contractor covers services outside the scope of OASIS II, the [...]
|
30/04/2015
|
|
17
|
Annex 2 Technical Specifications, Section 6, Service Modules Project Management is foreseen in “Complex [...]
|
As stated in the Annex 2.6 (chapter 1: Service Objectives), the Architecture Office is responsible for [...]
|
30/04/2015
|
|
16
|
In Annex 1.3 - Reference Form page 3, "Volume of deliveries": in this section, we understand that we [...]
|
The reference representing at least 4000 TB of disk-based storage should at least mention the number [...]
|
22/04/2015
|
|
15
|
On annex 1.4-technical evaluation questionnaire, page 4 it is stated that we have to create an strategy [...]
|
The contracting authority confirms your understanding: the strategy paper mentioned in section 3 of Annex [...]
|
22/04/2015
|
|
14
|
On technical specifications page 12 under point 5.3 it is stated: “The tenderer will have to provide [...]
|
The contracting authority confirms that the quote from point 5.3 of the Tendering Specifications – Main [...]
|
22/04/2015
|
|
13
|
In the technical selection questionnaire, the question 1.2.1 requires the tenderer to submit a 1 CV for [...]
|
The contracting authority confirms your understanding. For the profiles in question 1.2.1 of Annex 1.3 [...]
|
22/04/2015
|
|
12
|
Could you please confirm our correct reading of the framework contract: in case of answer based on joint [...]
|
The contracting authority confirms that references of subcontractors can be used in question 1.3.1 of [...]
|
22/04/2015
|
|
11
|
It is stated "have you included, as proof of experience, at least 3 references for similar contracts. [...]
|
The contracting authority confirms your understanding that you can provide more than three references [...]
|
22/04/2015
|
|
10
|
On Annex 1.3. page 5 of 18, under point 1.3.1 it is requested: "These references should contain at least [...]
|
The contracting authority does not confirm your understanding: it is expected from tenderers to submit [...]
|
15/04/2015
|
|