9
|
For technical selection criterion 3.1 in the additional information document, you have specified that [...]
|
The total budget of each of the 2 projects should be at least 5.000.000 EUR.
|
14/06/2021
|
|
8
|
In the Contract Notice, section 17/3.2, it says that "The candidate (i.e., the consortium as a whole, [...]
|
Implementation in countries listed on the World Bank's 2021 List of Fragile and Conflict-affected Situations [...]
|
14/06/2021
|
|
7
|
In the Contract Notice, under section 17/2.2, it is mentioned that "The candidate must at least have [...]
|
The experience requested under this criterion refers to previous experience with EU institutions and [...]
|
14/06/2021
|
|
6
|
In the Contract Notice, under section 17/2.2, it is mentioned that "The candidate must at least have [...]
|
This should be reflected in the EOI under No.6 EXPERIENCE - Detailed description of project and type [...]
|
14/06/2021
|
|
5
|
In the Contract Notice, under section 17.3 "Technical capacity of candidate", it is mentioned that "the [...]
|
The candidate should indicate their previous experience in each of the areas mentioned whether in one [...]
|
14/06/2021
|
|
4
|
In the Contract Notice, under section 17.3 "Technical capacity of candidate", it is mentioned that "the [...]
|
The candidate should indicate their previous experience in one of the areas mentioned (experience in [...]
|
14/06/2021
|
|
3
|
Could you confirm that the budget (5 000 000 EUR) of the projects implemented within the reference period [...]
|
The eligibility period is at any moment during the last 5 years before the submission deadline.
|
14/06/2021
|
|
2
|
Question 2: With regards to point 17.3 “Technical capacity of the candidate”: The reference period which [...]
|
The share of the candidate (in case of a consortium) must be significant and at least 50% for one and [...]
|
14/06/2021
|
|
1
|
Question 1: In the additional information about the Contract Notice point 17.2. “Professional capacity [...]
|
This should be reflected in the EOI under No.6 EXPERIENCE- Detailed description of project and Type and [...]
|
14/06/2021
|
|