Call for tenders' details

Kindly note that the Time limit for receipt of tenders has been extended until 05/11/2021, at 17:00 UTC+02:00.
Title:
Transversal Operations Framework (TOF)
Contracting authority:
European Agency for the Operational Management of Large-Scale IT Systems in the ...
TED publication date:
20/08/2021
Time limit for receipt of tenders:
05/11/2021
Status:
Closed
Show filter parameters

Results per page: 10 | 25 | 50 490 Questions found, displaying 1 to 10.[First/Prev] 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15 [Next/Last]
# Question Answer Last publication date Status
490
In Annex 1.2 Description of Services, in § 2.1.5.4, “The TOF Lot 2 Contractor shall: - Provide and maintain [...]
We confirm that it refers to the Contractor(s) own plans. The Contractor(s) shall maintain their own [...]
29/10/2021
489
According to the Legal Entity Form, each participating entity should sign and stamp the form. It is our [...]
Please, refer to Question & Answer no. 400.
29/10/2021
488
Regarding the Non-Business Hours multiplier could you please confirm our understanding that since only [...]
It is the Tenderer's responsibility to define its own pricing strategy regarding this element from the [...]
29/10/2021
487
With reference to the last point of question 2.11 (Lot1) could you please clarify to which of the following [...]
The correct reference of the term “non-regression” is in line with point (c) of the Question raised. [...]
29/10/2021
486
Section 2.4.5.1 on p 59 of Annex 1.1 Lot 1 DoS states that "TOF Lot 1 Contractor will test the fixes [...]
The Contracting Authority expects the Lot 1 Contractor, as part of the required “non-functional tests [...]
29/10/2021
485
In Section 2.4.5, it is stated: “The maximum price for the different typologies is selected and multiplied [...]
The question is not clear. However, as stated in section 2.4.3 of the Annex 7.1.3 - Lot 1 Pricing Model [...]
29/10/2021
484
In Section 2.4.3, it is stated: “The track record is based on the monthly average of incidents, problems [...]
a) Your understanding is correct. b) The volumes of the 2 remaining environments are not used in the [...]
29/10/2021
483
We request eu-LISA for an extension of 2 weeks due to the fact that the answers to Clarification round [...]
At the given moment, there is no provision for extension of the time limit for receipt of tenders; it [...]
29/10/2021
482
As we are approaching the Clarification question deadline for round 5 and eu-LISA has not yet responded [...]
At the given moment, there is no provision for extension of the time limit for receipt of tenders; it [...]
29/10/2021
481
In Annex 1.1 lot 1, section 2.4.12.6, is it mentioned that the Contractor must provide Capacity Analysis [...]
The TEF Lot 1 Contractor will be coordinating the gathering of inputs from the relevant TEF and TOF Contractors [...]
29/10/2021