190
|
Lot 1, Malawi case study: Does the exclusive engagement of a senior expert bounded by a long term contract [...]
|
Please see answers to question 79 clarifying the purpose of the case study and answers to questions 73 [...]
|
09/10/2015
|
|
189
|
In section 7.3.2. of the ToR, “Facilities to be provided by the Framework Contractor”, it is stated that [...]
|
Please note that Annex B 0 II Global terms of references has been modified in sections 7.3.2 and 8.4 [...]
|
09/10/2015
|
|
188
|
Would any graphic design costs (see Section 7.3.1 of ToRs) be reimbursable, since the extent of services [...]
|
The “other costs” will be specified in Specific terms of references. Please note that Annex B 0 II Global [...]
|
09/10/2015
|
|
187
|
When interviews will need to be conducted for specific contracts (section 8.4 of the Global terms of [...]
|
Interviews conducted for specific contracts will be remotely and cannot be reimbursed on any basis. Please [...]
|
09/10/2015
|
|
186
|
Can the inputs of the Contract Manager be reimbursed for specific contracts?
|
No. Please note that Annex B 0 II Global terms of references has been modified in sections 7.3.2 and [...]
|
09/10/2015
|
|
185
|
The ToRs include both Quality Manager and Quality Support Expert. Please confirm whether the inputs of [...]
|
No. Please note that Annex B 0 II Global terms of references has been modified in sections 7.3.2 and [...]
|
09/10/2015
|
|
184
|
Lot 1 Evaluation: Annex D I – Tender Submission Form, section 5 Declarations: “As part of their tender [...]
|
There are two declarations for the tenderer to sign. It is not two copies of the same declaration 1. [...]
|
09/10/2015
|
|
183
|
Lot 1: The Global Terms of Reference Lot 1: Evaluation, section 7.2.2 Experts (p. 7 of 15) state “c) [...]
|
We confirm that the relevant diploma and experience for Junior experts is what indicated in Annex B II [...]
|
09/10/2015
|
|
182
|
Lot 1: The Global Terms of Reference Lot 1: Evaluation, section 7.2.2 Experts (p. 7 of 15) state “d ) [...]
|
We confirm that the relevant experience for Project manager is what indicated in Annex B II 0 Global [...]
|
09/10/2015
|
|
181
|
Lot 1: ITT section 4.2.2 (p.5 of 14) Technical and professional capacity criteria// certification of [...]
|
We confirm answer to question 75 and agree on including phone and email addresses in a separate page.
|
09/10/2015
|
|