84
1. We understand that technical capacity will be assessed on the basis of the references submitted within [...]
1. The technical capacity of candidates will be assessed on the basis of the requirements set in the [...]
20/01/2022
83
With reference to the Question n 43 and its reply, could you please confirm that, in case the statement [...]
With reference to the Question n 43, for the purpose of the assessment of the Economic and financial [...]
12/01/2022
82
Is there any other means than completion letter and final payment evidence documents authorized to prove [...]
See question Question75
12/01/2022
81
Considering a project implemented by the Consultant and its local subsidiary, in which the Consultant [...]
Please see the information provided in the instructions to tenderers: with regard to criteria relating [...]
12/01/2022
80
As per the Tender Dossier and associate templates, our understanding is that a legal entity can include [...]
Your understanding is correct.
12/01/2022
79
Is a contract implemented for the Organisation of Eastern Caribbean States (OECS) eligible as a reference [...]
If the services provided under a reference were mainly delivered in or to the benefit of other member [...]
12/01/2022
78
1. Lot 1: Environment – In the Instructions to Candidates, under Technical Capacity of tenderer 3 (a5 [...]
(1) see question Question44 (2) we confirm that a project reference can only be used once in each tender [...]
12/01/2022
77
With reference to the Question n 43 (submitted on December 22), could you please confirm that, in case [...]
As specified in the instructions to candidates, the participation of an ineligible natural or legal person [...]
12/01/2022
76
Could you please confirm that multiple contracts under one framework agreement can be considered as one [...]
In the case of call off contracts awarded in the frame of framework agreements each call-off contract [...]
12/01/2022
75
Is an email from the client approving the final or the completion report enough to prove completion of [...]
Such evidence will be accepted, provided that the information included in the e-mail makes clear reference [...]
12/01/2022