Call for tenders' details

Title:
Supply, installation and maintenance of 2 battery storage systems - 2 lots.
Contracting authority:
European Commission, Joint Research Centre (JRC)
TED publication date:
31/07/2015
Time limit for receipt of tenders:
28/09/2015
Status:
Closed
Show filter parameters

Results per page: 10 | 25 | 50 53 Questions found, displaying 1 to 10.[First/Prev] 1, 2, 3, 4, 5, 6 [Next/Last]
# Question Answer Last publication date Status
1
The point C9 page 6 refers on the containment system: container 20 ft. Is it possible to use even systems [...]
20 ft container is the maximum dimension, there is no problem by using a smaller container if the security [...]
07/09/2015
2
The point D 14 page 6 refers to the “control unit”. The ‘control unit’ shall be understood as the supervisor [...]
The control unit shall be able to connect to a SCADA system. Some specifications of the SCADA are available [...]
07/09/2015
3
At the point D14 page 6 is defined the container in which the batteries will be installed, but it is [...]
The AC/DC converter must not be in the same container with the batteries. The container is located outside [...]
07/09/2015
4
Please clarify if the deadline of 14 September is actually valid for both - offers and requests to participate [...]
The deadline of 14 September specified in the Contract Notice is the deadline to submit the technical [...]
07/09/2015
5
Where is it possible to find the Contract Notice and the templates of the administrative documents to [...]
On the site ‘'Ted - eTendering' please go to section ‘TED’. At the top, almost centrally there is a link [...]
07/09/2015
6
Question 1: In respect to the documents to be provided by the tenderer, including by the “sub-contractor [...]
1. Subcontractors shall submit the same documents as the main contractor; the document in copy for the [...]
07/09/2015
7
Question: In the document “Technical specifications” on page 8, third point, it refers to a range between [...]
The unit of measurement is VAR and not VOLTS. The correct values are -60kVAR < Q < +60kVAR for [...]
07/09/2015
8
Question: In the document “Technical Specifications” on page 8, point 7th, it is defined a complete cycle [...]
For the lot 1 the correct value is 150 KWh and not 1 MWh. For the lot 2 the correct value is 450 KWh [...]
07/09/2015
9
Question: In the document “Technical Specifications” on page 8, point 8th, Is the word ‘... 1 MWh capacity [...]
The maximum capacity for the lot 1 is 150 kWh and for lot 2 is 450 kWh. The complete cycle per day (24 [...]
07/09/2015
10
Referring to the Contract Notice, must the technical and financial offer be prepared in a free format [...]
The technical and financial offer must follow the structure indicated in the Administrative Annex at [...]
07/09/2015