34
In the formula for the calculation of liquid damages, the value of "d" is given by the sum of the total [...]
"d" refers to each duration mentioned in the article I.2.3. (respectively: 5 months, 2 years, twelve [...]
09/09/2015
Answered
33
In the penultimate paragraph, what is meaning of the term "Smooth" relatively to connections and disconnections [...]
Please see the response to question 27
09/09/2015
Answered
21
Therefore also the sub-contractors must submit: - cover letter - declaration of honor - document issued [...]
For both lots: Subcontractors identified as per heading III.1.3 of the Contract Notice must provide a [...]
09/09/2015
Answered
12
Is the converter located in the enclosure indoor or outdoor? If it is placed in an open space, we have [...]
The converter in the enclosure will be place indoor (inside a building) There is no need for an extra [...]
08/09/2015
Answered
11
Referring to the Contract Notice, is it possible to submit the offer in Italian?
The tender may be drawn up in any official language of the European Union, including Italian.
07/09/2015
Answered
10
Referring to the Contract Notice, must the technical and financial offer be prepared in a free format [...]
The technical and financial offer must follow the structure indicated in the Administrative Annex at [...]
07/09/2015
Answered
5
Where is it possible to find the Contract Notice and the templates of the administrative documents to [...]
On the site ‘'Ted - eTendering' please go to section ‘TED’. At the top, almost centrally there is a link [...]
07/09/2015
Answered
4
Please clarify if the deadline of 14 September is actually valid for both - offers and requests to participate [...]
The deadline of 14 September specified in the Contract Notice is the deadline to submit the technical [...]
07/09/2015
Answered
9
Question: In the document “Technical Specifications” on page 8, point 8th, Is the word ‘... 1 MWh capacity [...]
The maximum capacity for the lot 1 is 150 kWh and for lot 2 is 450 kWh. The complete cycle per day (24 [...]
07/09/2015
Answered
8
Question: In the document “Technical Specifications” on page 8, point 7th, it is defined a complete cycle [...]
For the lot 1 the correct value is 150 KWh and not 1 MWh. For the lot 2 the correct value is 450 KWh [...]
07/09/2015
Answered