31
|
1) You are allowing digital signature and I checked that all the requirements that you have set in place [...]
|
1. Frontex uses an e-IDAS compliant solution producing documents in the PDF format adhering to the PAdES [...]
|
23/02/2022
|
|
30
|
As you mentioned in the answer to one of the questions: "“The established FWC shall enable Frontex with [...]
|
At this point, Frontex cannot engage to provide any planning of specific ordering, therefore the tenderers [...]
|
17/02/2022
|
|
29
|
We ask the client to postpone the deadline for the submission of tenders until 03. 03. 2022 as the shortage [...]
|
The deadline was already extended once as per the Corrigendum of the Contract Notice. The Contracting [...]
|
17/02/2022
|
|
28
|
The order quantity indicated in the tender is 5000 pcs. Should it be delivered at one time to each of [...]
|
As mentioned in Annex II Technical Specifications art. 3.1. “The established FWC shall enable Frontex [...]
|
17/02/2022
|
|
27
|
It seems that half of the question no 3 were missing from my original question, I am sorry. Now the full [...]
|
As described under point III.6 of the Tender Specifications in regard exclusion criteria:"Tenders involving [...]
|
17/02/2022
|
|
26
|
Our company will be the tenderer but another company (outside EU) will make production of the items. [...]
|
Kindly note, that according to Tiltle I, Article 2, point 61 of the Regulation (EU, Euratom) 2018/1046 [...]
|
17/02/2022
|
|
25
|
1) I understand that we need to submit Declaration of Honor about us and also about all the subcontractors [...]
|
We confirm that supportive evidence needs to be submitted with the tender. The documents to be submitted [...]
|
17/02/2022
|
|
24
|
Tenderer is obliged to provide a list of contracts performed during the last 3 years which correspond [...]
|
The values of the contracts must be reflected in the the currency of the relevant contract. EU institutions [...]
|
17/02/2022
|
|
23
|
If we have made multiple different samples, that for us seem to meet all the requirements but have a [...]
|
Kindly refer on Section II point 10 and 11 of the Contract Notice. No variant and no options weill be [...]
|
17/02/2022
|
|
22
|
As written in a.m. point, "Documents confirming fulfilment of the exclusion criteria as requested in [...]
|
The documents to be submitted are described in point VI of Annex V. As described in point III.3 of the [...]
|
15/02/2022
|
|
21
|
In Technical Specification sec 1.6 you state following: “For all subcontractors, regardless its share [...]
|
Answer 1: The description can be in an open format, it needs to be part of your offer clearly stating [...]
|
15/02/2022
|
|
20
|
Hello! Just to be extra sure that we have understood correctly here is a follow up question #3. In the [...]
|
Yes, your understanding is correct.
|
10/02/2022
|
|
19
|
Hi, referring to the corrigendum notice 2022/S 020-045283 dated 28 Jan 2022, the deadline for submission [...]
|
We hereby confirm that the new submission deadline is 24/02/2022 as shown in the Corrigendum.
|
08/02/2022
|
|
18
|
1. Do all of the attachments need to be signed? If so, is it require to sign them separetely or ZIP them [...]
|
A1: Kindly refer to the Invitation to Tender which clearly describes the tender submission process and [...]
|
07/02/2022
|
|
17
|
Hello! COuld you please include Frontex logo that needs to be printed on the armband in both pdf and [...]
|
The full vectorised file with Frontex logo will be provided to the selected contractor upon the contract [...]
|
03/02/2022
|
|
16
|
Is it possible to submit an offer in other language than English, e.g. Polish? Do reference letters and [...]
|
According to point 3 of the Invitation to Tender, we highly prefer tenders to be submitted in English [...]
|
27/01/2022
|
|
15
|
Good morning, I would like to kindly ask you to refer to the below issues regarding the following invitation [...]
|
A1.: Please referrer to the answer to the 1st question; in principle all market operators who can demonstrate [...]
|
26/01/2022
|
|
14
|
Dear Team, We are a quite new company, and I wanted to ask if this is possible for a small businesses [...]
|
Please note, that tenderers need to comply with the exclusion and selection criteria in order their tender [...]
|
25/01/2022
|
|
13
|
Good afternoon, we have two questions, first, we are non/european company based in Bosnia, and we would [...]
|
1.Under the Stabilisation and Association Agreements (SAA) economic operators established in North Macedonia [...]
|
25/01/2022
|
|
12
|
Can you be so kind to answer on our previous question from yesterday?
|
Your previous question is under assesment. An answer will be publised as soon as it duly prepared. Please [...]
|
25/01/2022
|
|
11
|
Could you please: 1. publish who is your current supplier 2. what kind of material currently used armband [...]
|
Please note, that we do not have any contract in place at the moment for the supply of armbands. Our [...]
|
25/01/2022
|
|
10
|
Could you please publish the drawing that this person who asked the question included in their question [...]
|
Kindly note, that there was no attachment submitted including any drawings to question2 by the tenderer [...]
|
24/01/2022
|
|
9
|
As you require samples and these need to be posted no later than 14.02 (ITT sec 4.1) could you please [...]
|
The submission of offers deadline can be exceptionally extended until 24 February 2022. The call for [...]
|
24/01/2022
|
|
8
|
You answered like this to question no 1: "The previous projects shall be within the category of the personalised [...]
|
Please refer on the supplementary answer published to question number 1.
|
24/01/2022
|
|
7
|
Please advise how many samples we need to submit (in pc)?
|
Following the requirements of the Annex I – Tender Specifications, point II.2.1.a.2 the tenderers are [...]
|
24/01/2022
|
|
6
|
In annex EN-5. Annex IV-Financial Proposal_1199_2021 you state the ordering quantity is 5000 pc. Is this [...]
|
The contract does not seek to establish a capacity for any particular one time or yearly quantity of [...]
|
24/01/2022
|
|
5
|
Please inform us how many samples must be submitted for the tender. Thank you.
|
Following the requirements of the Annex I – Tender Specifications, point II.2.1.a.2 the tenderers are [...]
|
24/01/2022
|
|
4
|
1. Regarding your reply for the total distance from edge to edge, to be 40cm with 10% variation, we have [...]
|
The contract does not seek to establish a capacity for any particular yearly quantity of the armbands [...]
|
24/01/2022
|
|
1
|
Good morning, referring to point III.4.3 and professional capacity from the tender specifications annexe [...]
|
Please note, that there was a typo in the priviously given answer. The correct answe is the following [...]
|
21/01/2022
|
|
3
|
1. How long is the total distance from one edge to the other, horizontally when open? As we estimate [...]
|
A1: the requirement expressed within Annex II Technical Specifications art.4.2.2. of 20 cm length with [...]
|
19/01/2022
|
|
2
|
We would like to make sure to which part of armband dimension given in Annex II Technical Specification [...]
|
Please refer to the Appendix 1 to Annex II – Technical Specifications: the 20 cm (variation 10%) length [...]
|
19/01/2022
|
|