7
|
1) Why, as a prerequisite, the transport of the soil samples should be done in refrigerate environment [...]
|
In accordance with the provisions of the section 1.2.3. Task 3 - Storage of the soil samples before the [...]
|
30/03/2016
|
|
5
|
2) Should the return of the soil samples be done in a refrigerate environment?
|
As the samples have to be dried prior to analysis, refrigerated transport is not necessary for the return [...]
|
30/03/2016
|
|
6
|
3) Is it possible to indicate approximately what is the volume of one piece of 500 g soil sample, respectively [...]
|
The approximate volume of a standard sample is 0.003375m3 (i.e. 15cm x 15cm x 15cm). However, it is possible [...]
|
30/03/2016
|
|
9
|
Referring to the procedure we would to ask if the containers for the soil samples to be collected are [...]
|
Individual soil samples are held in labelled plastic bags that are stored in groups in cardboard boxes [...]
|
31/03/2016
|
|
10
|
Referring to the procedure we would to ask if the containers for the soil samples to be collected are [...]
|
Please see answers for the question 8 and for the question 9. The containers for the residual soil sample [...]
|
31/03/2016
|
|
8
|
Referring to the procedure we would to ask if the containers are packed and sorted subject to the structure [...]
|
The samples are not ordered by the groups indicated in the schedule of analysis. The samples are held [...]
|
31/03/2016
|
|
24
|
Is it possible to organize a site visit? If yes, which is the modality?
|
Please see the answer to the question 16
|
07/04/2016
|
|
14
|
In case of awarding the contract, which is the date of starting the activity
|
As foreseen at the article I.3.3. of the contract – "Performance of the contract starts from the date [...]
|
07/04/2016
|
|
21
|
As regards the criterion T5 "at least one member of the team shall be able to communicate at least at [...]
|
At this stage the contracting authority cannot make assessment of one tender, it is the responsibility [...]
|
07/04/2016
|
|
1
|
Referring to the Contract Notice in question we would like to know the site for collection of samples
|
In accordance with the provisions of the Technical Specifications (Ares(2016)1102630 - 03/03/2016), part [...]
|
16/03/2016
|
|