Results per page: 10 | 25 | 50 22 Questions found, displaying 1 to 10.[First/Prev] 1, 2, 3 [Next/Last]
# Question Answer Last publication date Status
4
Can an American company participate? If so, can they send in a bid for Lot 4 only? What is the procedure [...]
It seems possible that a US based economic operator can participate in this specific procurement for [...]
01/04/2016
1
Dear DG Sante Procurement Team, It is not absolutely clear what exactly should be the content/structure [...]
The technical offer should contain all elements needed to demonstrate that it matches the technical specifications [...]
21/03/2016
10
Dear Madame and Sir, in what size should the single-use aprons, impermeable gowns and surgical scrubs [...]
The median size distribution in a "working population" is genereally assessed as being as follows: 10% [...]
22/04/2016
7
Dear Mr. or Madame, is it possible for an organization to participate to a single Lot ?
Yes it is possibole to paricipate to a singlée lot.
18/04/2016
9
Dear Mr./Madame, related to the Lot 5 (Occupational foot wear) we would like to have some clarifications [...]
EN ISO 20347-2012 provides all infroamtion nedded to prepare an offer. Nevertheless you will find hereunder [...]
21/04/2016
6
Dear Sir / Madame, can you please advise on the requirement EN 374-1:2003: Minimum permeation performance [...]
We confirm that the required minimum breakthrough time is above 120 minutes (for commonly used disinfectants [...]
13/04/2016
21
Dear Sirs, how can we calculate the transport costs for each item? We need do imagine the minimum quantities [...]
A "transport" will most probably be for a certain quantity (depending on the packaging of each item) [...]
27/04/2016
8
Dear Sirs, filling in the Annex IX - simplified presentation viability checks pur total score i 7 point [...]
Good morning, The field with the final decision is not an automatic field the "YES/NO" will be introduced [...]
21/04/2016
5
Figures in Annex I "Needs analysis per buyer and per lot_final" are valid for the entire 4-years contract [...]
This is a framework contract that will be signed for a 36 months period and might be prolonged for a [...]
04/04/2016
20
If I understand correctly, the requirement for delivery within 72 hours when called for, means that supplier [...]
There is no "requirement/indication" as to how long the supplier should hold the stock as we have no [...]
27/04/2016