9
|
Conflict of interest: We take good note of the provisions included in the Instructions to Tenderers ( [...]
|
1) Yes. Please see answer 1. 2) Yes. Please see answer 1. 3) All candidates have to demonstrate their [...]
|
02/09/2016
|
|
11
|
Could you please confirm that eventual weaknesses in the methodological approach to potential conflict [...]
|
Please see answer to question 10.
|
02/09/2016
|
|
4
|
Could you please confirm that no conflict of interest will involve, a priori, Framework Contractors leader [...]
|
The onus is on the tenderer to produce a methodology to ensure conflict of interest, including potential [...]
|
29/08/2016
|
|
10
|
Could you please confirm that no potential conflict of interest of the tenderer will automatically revert [...]
|
Inability to adequately report and avoid/mitigate possible professional conflict of interest will results [...]
|
02/09/2016
|
|
13
|
Do members of the core team need to be EU nationals? If not, will the EC assist in securing work visas [...]
|
The core team can be non-EU nationals; there is no restriction on the nationality of the core team. The [...]
|
07/09/2016
|
|
8
|
In the technical capacity criteria, it is stated that the language of contract must be either French [...]
|
Such a contract would be acceptable if the principal language of the contract was French or English ( [...]
|
30/08/2016
|
|
12
|
Is prior evaluation experience with DEVCO required to take part in the tender?
|
We would like to clarify that prior DEVCO evaluation experience is not required for the purpose of this [...]
|
05/09/2016
|
|
2
|
On p. 12 the ToR mention January 2016 as intended start date of the contract. Are we right to assume [...]
|
The estimated start date of the contract is January 2017. Please see Instructions to Tenderers point [...]
|
22/08/2016
|
|
3
|
On p. 13 the ToR state that “one full-time post (with the exception of the Team Coordinator) could be [...]
|
A further line can be added to ensure you can show two part time posts (with days showing 440 for each [...]
|
29/08/2016
|
|
6
|
On p. 15-16, the ToR list requirements for potential non-core experts. Are we right to assume that it [...]
|
The tender documents set out which CVs are required at the tender stage. CVs of non-core experts were [...]
|
29/08/2016
|
|