9
|
(Reformulation) Financial proposal: The proposed term for the contract is 4 years. Can the bidder propose [...]
|
No, price revision is already defined in the draft contracts.
|
06/10/2016
|
|
2
|
Administrative: if we submit a tender for both Lots 1 and 2, do we need to send as separate envelopes [...]
|
As stated in the Tender Specifications under point 2.1, If a tenderer wishes to submit a bid for both [...]
|
06/10/2016
|
|
3
|
Annex II - 2.2.1. "It should be noted that the Commission does not have any capability for direct transmission [...]
|
Yes.
|
06/10/2016
|
|
10
|
Does EbS requires the insertion of the EPG data directly at Berlaymont facilities or can this be delivery [...]
|
The EPG/SI generating equipment should be located at the Berlaymont building, as stated in the Technical [...]
|
19/10/2016
|
|
12
|
How do you feed the EPG Generator? Do you use xml files? Do you need to edit your scheduled events?
|
The EPG generator is updated every 3 minutes through the feed of xml files.
|
26/10/2016
|
|
4
|
In Annex I, page 6, chapter 2.2.2, it is stated "This service comprises: - Ad hoc transmissions (by satellite [...]
|
There is no inconsistency. The Tender Specifications (Annex I) expresses the need for bi-directional [...]
|
06/10/2016
|
|
7
|
In Annex II, page 3, chapter 2.1.1 , for point 1(a), it is stated "Dish sizes must be similar to those [...]
|
The EbS and EbS+ services were migrated recently to Eutelsat 9B, due to the discontinuity of the service [...]
|
06/10/2016
|
|
5
|
In Annex II, page 4, chapter 2.1, for point 3(a), it is stated "The content of the four original HD-SDI [...]
|
The 4 original HD-SDI signals are: 1 - EBS with embedded audio channels 1 - 16 2 - EBS with embedded [...]
|
06/10/2016
|
|
1
|
In the Contract Notice 2016/S 182-326121 -Belgium-Brussels: Provision of transmission services, the estimated [...]
|
The total estimated value of 4 100 000 EUR is the maximum budget for both Lots for the maximum duration [...]
|
05/10/2016
|
|
11
|
In the financial offer there are 2 parts, the total quarterly price for complete provision of transmission [...]
|
Correct. The optional prices are not to be included in the total quarterly price for Lot I(a) and Lot [...]
|
25/10/2016
|
|