1
most recent figures are required but 2012 figures are still provisional. Please confirm whether economic [...]
As per Section no 5.2.2 of the Tender Specification, the tenderers should provide: a) A full copy of [...]
03/07/2013
Answered
2
Documents in DRL: can we propose mergers/optimisations?
Yes, provided that the mergers and optimisations are duly justified as explained is 6.10.2.
03/07/2013
Answered
3
Please confirm that an independent Power of Attorney per each member of the consortium can be provided [...]
Each member of the group should provide an independent Power of Attorney, as specified in section 2.7 [...]
03/07/2013
Answered
4
The DRL asks for a ‘product tree’. How should it be understood, as the catalogue of products generated [...]
The product tree should present the entirety of the products created or delivered under this contract [...]
03/07/2013
Answered
5
Please, confirm that the use of PSS and ECOS for financial proposals is optional.
As specified in the ITT, section 6.10.2.1, PSS-A1, PSS-A2 and PSS-A8 should be used. ECOS files do not [...]
03/07/2013
Answered
6
Will all documents referred in section 6.10.2 Product Assurance, Safety and Engineering Standards, be [...]
Yes
16/07/2013
Answered
7
Sections 6.8.3 (Key Operational Concept) and 6.8.4 (Operational Interfaces) of the SC1-SoW, include references [...]
The GNSS Service Centre will have an interface with the CS provider. The location of the CS provider [...]
16/07/2013
Answered
8
This document is not requested for the Hosting Service Contract (SC2). Is it relative to the overall [...]
As presented in the section 6.11, this document is needed for the Specific Contract N°1
16/07/2013
Answered
9
No input CSAR has been identified in the CISL. CSAR identified as a document to be completed in line [...]
CSAR is defined is annex 6.14 of the ITT. See section 2.19 Configuration Status Accounting Report (CSAR [...]
16/07/2013
Answered
10
Clarification required on the scope of all this documentary package. In the assumption this documents [...]
The tenderer should present his QMS plans, manual and procedures. It is up to the tenderer to present [...]
16/07/2013
Answered