Results per page: 10 | 25 | 50 15 Questions found, displaying 1 to 10.[First/Prev] 1, 2 [Next/Last]
# Question Answer Last publication date Status
1
Could an entity involved in the implementation of the previous pilot projects be eligible to submit a [...]
The conditions for submitting a tender are clearly described in the ToR for exclusion and selection criteria [...]
12/04/2013
2
In article 2.3.2. of the Tender specifications its stated that we need to provice the CV's of the team [...]
According to article 2.3.2b on Technical and professional capacity criteria and evidence the tenderer [...]
02/05/2013
3
Is it allowed to submit scanned signatures or do they need to be original? Also, we need to submit the [...]
All signatures must be original. For the "legal entity" and "financial identifiation" form, a copy will [...]
07/05/2013
4
The TORs explicitelly mention reference systems, data collection, etc. that are part of the 2013 IPs [...]
The requested implementation plans form an integral part of the Specific agreements signed between the [...]
07/05/2013
5
For which of the 27 member states it is required to produce water balances at sub-basin level. Are these [...]
The geographical scope should cover the catchments included partially or totally in EU Member states [...]
13/05/2013
6
Do the water balances have to be produced on sub-basin level and then being aggregated to basin level [...]
Water balances have to be produced at sub-basin level, enabling further aggregation at river basin district [...]
13/05/2013
7
Which basins from part of the group ‘best documented basins’ for which at least it is required to produce [...]
the question raise concerns on the proper understanding of what is required in the technical specifications [...]
13/05/2013
8
Aside from the existing databases, can we also make use of the instruments (like NOPULU System and AQUATOOL [...]
The mentioned tools were used by former contractors for the production of water accounts. The tenderer [...]
13/05/2013
9
In the tender specifications it is specified on page 13 under task 2 sub 1: "The contractor should revise [...]
As mentioned in the tender specification some inconsistencies with the water bodies between Ecrins and [...]
13/05/2013
10
Please provide additional insight in to the amount of work that is to be expected to make the databases [...]
The objective of the tender and the tasks are clear and cannot be modified. The gaps are precisely described [...]
13/05/2013