1
|
Is a strong participation in FP7 projects a limitation for the eligibility of a tenderer?
|
A strong participation in FP7 does not constitute a limitation for the eligibility of a tenderer.
|
16/06/2017
|
|
2
|
This annex is referred as an excel within the ToR. However, there is no possibility to download it in [...]
|
The Annex 7 in excel has been uploaded in the document library.
|
20/06/2017
|
|
3
|
According to section 4.2.4 technical and profesional capacity criteria and evidence, point A (page 27 [...]
|
Indeed, we confirm that the evidence must be provided only on request and does not have to be submitted [...]
|
22/06/2017
|
|
4
|
Our understanding is that subcontractors do not need to provide legal entity and supporting documents [...]
|
We confirm that your understanding is correct and subcontractors do not need to provide legal entity [...]
|
22/06/2017
|
|
5
|
If the consortium members of a joint tender already cover the mínimum criteria for the economic and financial [...]
|
Your understanding is correct. Criteria F1 is applicable to the tenderer as a whole, therefore the evidence [...]
|
22/06/2017
|
|
6
|
We would really appreciate if you could share the Annexes in Word (e.g.: declaration on honour, letter [...]
|
Anexes in Word format have been uploaded to the Document Library.
|
23/06/2017
|
|
7
|
Task 4 is not included in the Award Criteria - “1: Quality and appropriateness of the tender for the [...]
|
It is correct, task 4 – training of EC staff is not included in the award criteria and no score will [...]
|
03/07/2017
|
|
8
|
Could the role of Business Analyst (TS p. 73) be divided in two different profiles according to different [...]
|
Yes, the profile for the Business analyst (Annex 12, Section 3, p. 73 of the tenders specifications) [...]
|
03/07/2017
|
|
9
|
According to the Tender Specifications (TS p. 8) sporadic ad-hoc surveys have already been launched. [...]
|
The ad-hoc surveys to which reference is made in the Tender Specifications, section 2.2.2. 'State of [...]
|
03/07/2017
|
|
10
|
Task 4 is not included in the Award Criteria - “1: Quality and appropriateness of the tender for the [...]
|
Question7
|
04/07/2017
|
|