1
|
Hello, We plan to submit a proposal for Lot 2. Apart from freelancers, we also plan to have internal [...]
|
As indicated in point 2.7.1 of the Specifications the document No 2 for lot 2 "Description of the internal [...]
|
17/04/2018
|
|
2
|
According to Technical Specifications (4.2.1) In 2017, law-making activity produced 1 033 legal acts [...]
|
Correction: the question is related to lot 1, not to lot 2. Around 2.2 million PDF pages have been ordered [...]
|
03/05/2018
|
|
3
|
According to Tender Specifications the required productivity is 45 000 pages/week (interim delivery) [...]
|
Correction: the question is related to lot 1 (point 4.2.4.4), not to lot 2. As indicated in the Tender [...]
|
03/05/2018
|
|
4
|
In the section 4.2.2 Production Scheme, it is implicated that in principle the source files are available [...]
|
Correction: the question is related to lot 1, not to lot 2. In the largest majority of the cases, source [...]
|
03/05/2018
|
|
5
|
The Formex format of the source file needs to be validated prior to pre-processing stage. What is the [...]
|
Correction: the question is related to lot 1, not to lot 2. This case is rather exceptional and concerns [...]
|
03/05/2018
|
|
6
|
Does/will/can the order-delivery procedure via IMMC be applied to the provision of services under lot [...]
|
Question related to Lot 2. The order-delivery procedure for Lot 2 is described in section 4.3.3.1 and [...]
|
03/05/2018
|
|
7
|
4.2.3.1 “The Publications Office may provide an access to the database containing information about legal [...]
|
The question related to lot 1. The usual production requests concern already published legal acts, i.e [...]
|
03/05/2018
|
|
8
|
4.2.3.7 b) amending text should be adapted according to the language's grammar rules (e.g. declinations [...]
|
Correction: the question is related to lot 1, not to lot 2. Linguistic adaptation as described in point [...]
|
03/05/2018
|
|
9
|
In point 4.2.5 of the technical specifications, "Start-up phase", it is indicated that the costs relating [...]
|
Q: c) If 1% of A + B + C + D items in Annex 2.A.'Estimation form' is not sufficient to cover the set-up [...]
|
08/05/2018
|
|
10
|
In point 4.2.3.7 of the technical specifications, "Consolidation", it is stated that during the project [...]
|
a) +b) No adaptation to a new version of FORMEX was required under the contract AO 10605. Consequently [...]
|
08/05/2018
|
|