On p. 19 ToR, the second sentence under the headline 'Creativity' is incomplete ('Both the degree.... [...]
|
The word 'Both' is present in this sentence due to a clerical error. The correct version of this sentence [...]
|
15/02/2018
|
|
2
|
Regarding profiles for criterion B5, do you mean that collectively all profiles should have a minimum [...]
|
As the professional and technical capacity critera differ between the lots, could you please clarify [...]
|
20/02/2018
|
|
3
|
Regarding the first part of criterion/Evidence A3. Would you consider a non EU project in ENI-East countries [...]
|
'a non EU project' is a project where the geographical scope covers a country that is not a member of [...]
|
20/02/2018
|
|
4
|
We have a question regarding the second part of criterion/Evidence A3 related to contacts in EU and non [...]
|
'a non EU country' is a country that is not a member of the European Union
|
20/02/2018
|
|
5
|
We have a question regarding the second part of criterion/Evidence A3 for lot 2 related to contacts in [...]
|
The TOR stipulates that: (…) the Tenderer must prove that it has contacts in the EU and in non-EU countries [...]
|
20/02/2018
|
|
6
|
Given the extensive 'Technical and professional capacity criteria and requested evidence' for both lots [...]
|
From 01/01/2018 the Legal minimum time limits for open calls are set at 37 days from the date on which [...]
|
21/02/2018
|
|
7
|
Regarding profiles for criterion B5 of lot 2, do you mean that collectively all profiles should have [...]
|
Collectivelly all profiles should have at least 5 years of proven experience
|
21/02/2018
|
|
8
|
Good morning, Regarding selection criteria of lot 2, can one project be proposed for several criteria [...]
|
It is up to the tenderer to decide which way to demonstrate the capacity in relation to selection criteria [...]
|
26/02/2018
|
|
9
|
Good morning, Regarding selection criteria for lot 2, can one expert be proposed for several profiles [...]
|
It is up to the tenderer to decide on the composition of the team he wishes to submit in its proposal [...]
|
26/02/2018
|
|
10
|
Original description With regard to the EU official language criterion A2, do tenderers have to be able [...]
|
The tender specifications stipulate for LOT 1 that accordingly to criterion A2 tenderers need to demonstrate [...]
|