1
|
Please kindly confirm whether there is currently a contract in force, providing the services foreseen [...]
|
There is currently a contract in force, which runs until the end of 2018. Details about the contractor [...]
|
11/06/2018
|
|
2
|
Could you please clarify if "the tendered must provide its capacity to work in 5 EU countries" should [...]
|
The tenderer must demonstrate that it is capable of providing a service in 5 different EU countries, [...]
|
25/06/2018
|
|
3
|
On page 26 of the tender specification, it is written that the Project Manager and the IT Operations [...]
|
For this specific requirement (criterion B2), the languages requested (EN, FR and / or ES) are those [...]
|
26/06/2018
|
|
4
|
Do university exams qualify as 'past relevant experience' to demonstrate C1 level in a given language [...]
|
Strictly speaking, academic (university) qualifications can be assimilated to a "past relevant experience [...]
|
10/07/2018
|
|
5
|
We note the following entry in the Draft Contract: Under I.5.2. Interim payments 1(c) In case of renewal [...]
|
Indeed, "500%" is a typo. It was meant to be "50%".
|
18/07/2018
|
|
6
|
The Answer provided to Question 2, regarding capacity to work in 5 EU countries reads:"The tenderer must [...]
|
Subject to an in-depth assessment of the details, such projects may meet the requirements of this criteria [...]
|
20/07/2018
|
|
7
|
Dear Sir / Madam. On page 17 of the specifications it is referred that an overview of the (IT) system [...]
|
The non-disclosure statement can be signed by the contractor, not by a tenderer. Therefore by definition [...]
|
24/07/2018
|
|
8
|
Has there been an evaluation of the services provided by the current contract, and if yes, where can [...]
|
The implementation of EUMOFA is being evaluated in the framework of the interim evaluation of expenditures [...]
|
25/07/2018
|
|
9
|
In relation to question 8, as a formal evaluation is yet to be completed, have there been any surveys [...]
|
Yes there have been surveys and - more generally - users feedback were taken into account as it is good [...]
|
26/07/2018
|
|
10
|
Reference made to point 2.2.2.2 Data Purchase where the contractor is expected to “allocate a part of [...]
|
The purchase of data from providers (public or private) is managed by the contractor. The Commission [...]
|
31/07/2018
|
|