Tender procedure "OJ/2017/ICT/9196" was closed by ECDC and re-opened under this "OJ/2018/ICT/9754". Under [...]
|
ECDC has taken into account the comments and questions related to tender OJ/2017/ICT/9196 and carried [...]
|
10/07/2018
|
|
2
|
The file "EN-12. Technical Annex 8 Draft Service Reporting-final word" is actually a PDF and not a DOCX [...]
|
A word version of the Technical Annex 8- Service Level Reporting has been published.
|
12/07/2018
|
|
3
|
The file "EN-9. Technical Annex 4 Draft SLA-republish v2_ElSi track change" is actually a PDF and not [...]
|
A word version of the “Technical Annex 4 –Service Level Agreement” has been published.
|
12/07/2018
|
|
4
|
In the document “EN-Tender Specifications_9754_IT_Service Tender_final” chapter 4.2 technical evalution [...]
|
We will evaluate how well fitting the initial proposed team is for delivering the services to ECDC, with [...]
|
12/07/2018
|
|
5
|
What will be approximate break up of intramural and extramural work?
|
Please see 2.2.7.4 of the tender specifications detailing the on site and off site work.
|
12/07/2018
|
|
6
|
Can be the extramural work be outsourced to a sub contractor located in India?
|
See 2.2.6.1 of the tender specification detailing that all data processing need to be done in the EU, [...]
|
12/07/2018
|
|
7
|
The ratio of projects that required EU cleared staff is a component of the pricing. Assuming that the [...]
|
This tender is about IT services and not about IT projects, so the question is not relevant for this [...]
|
12/07/2018
|
|
8
|
We understand that intramural services need to be performed at Solna, Sweden - Is this correct?
|
Indeed the intramural work will be performed in ECDC, which is located in Solna, Sweden.
|
12/07/2018
|
|
9
|
Is it mandatory that the extramural work need to be done from European Union, European Economic Area [...]
|
See 2.2.6.1 of the tender specification detailing that all data processing need to be done in the EU, [...]
|
12/07/2018
|
|
10
|
If the work is subcontracted who needs to provide references , the contractor or subcontractor?
|
The reference should be provided by the party that will execute the major part of the work. In case of [...]
|