1
|
Our Technical Department have submitted the following request fro clarifications regarding the opportunity [...]
|
6)There is no single solution to physically connect the photovoltaic (PV) solar panels to the roof of [...]
|
19/06/2019
|
|
2
|
You have stated in the tender document that the minimum system output needed is 80kWp while you have [...]
|
Section 5.2 of the technical specifications shows the scoring assessment matrix that will be applied [...]
|
19/06/2019
|
|
3
|
Question (1) Technical Specifications - Page 12 - Section 3.2 Para.#3 &Para.#5, 1st bullet point. [...]
|
Answer (4): The base load on a grid is the minimum level of demand on an electrical grid over a span [...]
|
19/06/2019
|
|
4
|
Question (4) Technical Specifications Page 9 - Section 12.1 Integration of PV power output into Electrical [...]
|
Please see the answers already published.
|
19/06/2019
|
|
5
|
1.7 Description of Building Please provide detailed roof dimensions for building 77. Is ti 780m² or 435m² [...]
|
Please see the documents uploaded in the documents library for answers to the questions n° 5.
|
25/06/2019
|
|
6
|
In your answers for different questions, you replied "see photos uploaded to the documents library". [...]
|
Please see the documents uploaded in the documents library for answers to the questions n° 5.
|
25/06/2019
|
|
7
|
We are intending to send some people on site to assess the Roof and building 77. Which date and time [...]
|
Please see the point IV.1. Visit of the "INVITATION TO TENDER" 001 version, where is mentionned: " 1. [...]
|
15/07/2019
|
|
8
|
As per Corrgendum, the deadline of this tender has been extended until 19/08/19, Could you be so kind [...]
|
Indeed, as per corrigendum the deadline for submission a tender is 19/08/2019. Regards
|
10/07/2019
|
|
9
|
1)- What is the thickness of the 40x40 roof purlins? 2)- We are planning to send someone on the site [...]
|
Answer 1) - The technical information available on the metal structure supporting the roof is as follows [...]
|
15/07/2019
|
|
10
|
The dimension which you have stated in the file "EN-Total+roof+area+m2” can not be seen at all. Can you [...]
|
It is planned to install solar panels on the surface of the roof: • Not including overhangs: 370 m² ( [...]
|
15/07/2019
|
|