It is noted under Section 5.2.1 of the Tender Specifications that the Project Manager for the study must [...]
|
Please note that it is a clerical error. Indeed, proven knowledge of German at the level of B.1 of the [...]
|
24/07/2019
|
|
2
|
According to the description of WP2, the tenderer will need to 'identify at least 3 good stories per [...]
|
The actual written stories need to be part of the deliverables.
|
26/07/2019
|
|
3
|
Could you please advise on how the tendering authority sees the difference between a 'story' and a 'message [...]
|
The story should be a real case of a company’s experience with public procurement, that can be inspirational [...]
|
26/07/2019
|
|
4
|
Work package II states 'Based on the SMEs participating in focus groups and other research methods, the [...]
|
Yes, this is correct understanding.
|
06/08/2019
|
|
5
|
Could you please confirm that the actual production of the messages will NOT be part of the deliverables [...]
|
Please note that the development of the key messages is in fact a key component of work package 2 and [...]
|
13/08/2019
|
|
6
|
According to the paragraph 5.2.3. Evidence of the technical and professional capacity of the service [...]
|
Regarding point b): the required evidence is requested for the legal entity and principal services are [...]
|
22/08/2019
|
|
7
|
Dear Madam/Sir, could you please clarify : • In case of involvement in the offer of self-employed persons [...]
|
• Self-employed persons working for the tenderer, without the tasks of the self-employed persons being [...]
|
02/09/2019
|
|
8
|
Could you please confirm if you consider the electronic signature based on the certificate issued by [...]
|
Yes, as IZENPE is on the national trusted list for the Qualified certificate for electronic signature [...]
|
09/09/2019
|
|
9
|
Could you please clear the following statement: "The tenderer (in case of a consortium or grouping and [...]
|
The tenderer must prove that the proposed team is readily capable to carry out the tasks described in [...]
|
12/09/2019
|
|
10
|
The Terms of Reference in Section 1.1.2 state that for Work Package 1, the contractor "should envisage [...]
|
The minimum requirement of three procedures refers to the number of instance. It can be only focus groups [...]
|
13/09/2019
|
|