Call for tenders' details

Title:
Support to the Kesrwan Water and Wastewater Project
Contracting authority:
European Investment Bank (EIB)
TED publication date:
07/10/2019
Time limit for receipt of tenders:
23/12/2019
Status:
Closed
Show filter parameters

Results per page: 10 | 25 | 50 38 Questions found, displaying 1 to 10.[First/Prev] 1, 2, 3, 4 [Next/Last]
# Question Answer Last publication date Status
1
We understand that responses to the clarifications will still be received on 20th of November 2019. Provided [...]
The deadline for tender submission will be postponed to 23/12/2019 at 19:00 Luxembourg time. Responses [...]
18/11/2019
2
Task 2.2: Please confirm that the concerned conceptual/detailed design would be for project components [...]
The task relates to assisting CDR with procuring the conceptual/detailed design as necessary. If designs [...]
02/12/2019
3
Task 1.2: it is stated that the TA Consultant shall review the state of progress of project implementation [...]
Task 1.2 refers to the entire project and not just the Jeita WWTP component. The task is not limited [...]
02/12/2019
4
Task 3.3: Please confirm that the preparation of tender documents for the two WWTPs is excluded from [...]
Your assumption is incorrect. The tender documents for any components for which the procurement has not [...]
02/12/2019
5
Task 3.3: Please confirm that the preparation of tender documents for primary and secondary wastewater [...]
Your assumption is incorrect. The tender documents for any components for which the procurement has not [...]
02/12/2019
6
Task 3.4: Please confirm that assistance during the procurement process covers only components that are [...]
Assistance during procurement will be required for all components. The nature of the assistance will [...]
02/12/2019
7
1- It is understood that the expropriation files will be prepared by the design consultants and not the [...]
1. Unfortunately we are not in a position to answer your question as what you mean by "expropriation [...]
02/12/2019
8
Can you please advise if prequalification of supervision consultants and/or contractors has been conducted [...]
The process is still ongoing.
02/12/2019
9
"Are these documents (points a to g in section 4.2) available for viewing at CDR? "
Tenders which are still under preparation shall remain confidential. Tenders already published can only [...]
02/12/2019
10
Accordingly and in order to better assess the efforts needed in relation to the TA Consultant’s scope [...]
The procurement process for the construction supervision consultant for the Ghazir component is currently [...]
02/12/2019