11
|
1) Does the Consultant as a whole and/or the Environmental Expert (KE3) must be registered as an environmental [...]
|
1) The registration can be obtained after the signature of the contract but the Consultant is expected [...]
|
09/01/2020
|
|
19
|
According our understanding of the TOR’s reading, the detailed design reports (including its annexes) [...]
|
The reports have to be provided at the same time for the 3 road sections. This is splitting of the Marginal [...]
|
09/01/2020
|
|
10
|
According to Terms of Reference, Annex A, Annex 3 (Geological and source of materials study), “the budget [...]
|
The investigation works are part of the Consultant's tasks. Thus, the cost of the investigations is borne [...]
|
09/01/2020
|
|
6
|
According to Terms of Reference, section 4.2, task 2: “The Consultant shall assess and implement an external [...]
|
According to the Terms of reference, the Consultant shall assess the training requirements and provide [...]
|
09/01/2020
|
|
27
|
According to Terms of reference, section 6.1 regarding Support staff and backstopping: “Note that the [...]
|
This is a clarification that the Consultant should not double budget for the support and backstopping [...]
|
09/01/2020
|
|
8
|
According to Terms of Reference, section 6.1, regarding Key Expert 4: “Key expert 4: Social Safeguards [...]
|
The "Sao Tome Professional experience" requirement, is a typo. It should be "Professional experience" [...]
|
09/01/2020
|
|
7
|
According to Terms of Reference, section 6.1, “in order to obtain the Environmental Permit, the Consultant [...]
|
We confirm that the registration can be obtained after the signature of the contract but the Consultant [...]
|
09/01/2020
|
|
9
|
According to Terms of Reference, section 7.2, progress reports must be both in Portuguese and in English [...]
|
The final approved version of the deliverables should be translated in Portuguese and submitted in e-copy [...]
|
09/01/2020
|
|
26
|
After analyzing the RFP of the tender regarding the Detailed project engineering design, bid documents [...]
|
Taking into account the constrains form the financing agreement, the deadline cannot be extended.
|
09/01/2020
|
|
25
|
Due to the reduced effective worktime during Christmas and New Year’s season and the difficulty in finding [...]
|
Taking into account the constrains form the financing agreement, the deadline cannot be extended.
|
09/01/2020
|
|