1
|
Via the Call for Tenders SMART 2019/1087, it was foreseen that there should be quickly a second phase [...]
|
SMART 2019/0094 "Digital European Platform for Quality Contents Providers" is not the continuation of [...]
|
11/05/2020
|
|
2
|
We can't find any indications as to when the contract will be awarded. Do you have a time schedule when [...]
|
The contract will be awarded in the last months before year-end, at the end of the procurement procedure [...]
|
13/05/2020
|
|
3
|
Is there any indication of a maximum budget of the contract?
|
The maximum amount of the contract is indicated under Sections II.1.5 and II.2.6 of the published Contract [...]
|
13/05/2020
|
|
4
|
For criterion T1, is it mandatory that the projects listed be in the field of media-related services? [...]
|
The technical and professional capacity criterion indicates that the tenderer must prove experience in [...]
|
28/05/2020
|
|
5
|
Could you please clarify the definition/role of the European digital distribution platform? Do you envisage [...]
|
The aim of the requested feasibility study is to inform policy making. The study should help European [...]
|
22/06/2020
|
|
6
|
Could you please clarify the legal framework analysis envisaged in Point 6 in Chapter 1.4.2 (pg 8 of [...]
|
According to Section 1.4.2. Point 6, a legal framework for the operation of the platform in question [...]
|
22/06/2020
|
|
7
|
Could you please clarify your expectations regarding the Cost Benefit Analysis described in Point 1. [...]
|
The feasibility study aims to enable the European policy makers’ informed decision making, to assess [...]
|
23/06/2020
|
|
8
|
1. We understand that the European Commission is the buyer with the Directorate General for Communications [...]
|
1. The Contracting Authority cannot disclose this information. For transparency and equal treatment reasons [...]
|
30/06/2020
|
|
9
|
We would like to subcontract a public institution to perform part of the services. Please advise on whether [...]
|
Economic operators are free to organise themselves as they wish (also with public institution). The list [...]
|
09/07/2020
|
|
10
|
We noted the proposed payment terms of 40% upon reception of the interim report. Given the long 9 months [...]
|
The terms already communicated cannot be changed. Submission of a tender implies acceptance of all the [...]
|
10/07/2020
|
|