Dear EMSA team, This call for tender is coming in a difficult period (summer vacations and Covid outbreak [...]
|
At the moment EMSA considers that the current duration of the bid submission period is sufficient to [...]
|
04/08/2020
|
|
2
|
Dear EMSA team, We have a question regarding to the place of performance where a part of the services [...]
|
Contractor's premises can be in a location in any continent across the globe if it is guaranteed that [...]
|
18/08/2020
|
|
3
|
For Module 1, FAT is forecast at T0 + 6months: does it mean that all developments within Module 1 for [...]
|
The scope of the Acceptance Tests (FAT, SAT#1, and SAT#2) is specified in Section 15 of “Appendix 1 TS [...]
|
20/08/2020
|
|
4
|
In the tender specifications, page 4, it is stated that 2 IT environments (Preproduction and production [...]
|
The Appendix I.59 describes the system and application technical landscape of EMSA and on page 12 are [...]
|
20/08/2020
|
|
5
|
What is the expected retention period for video footages ?(Do they have to be stored and made accessible [...]
|
The Data Storage requirements are described in Section 10 of “Appendix 1 TS – Technical Requirements” [...]
|
20/08/2020
|
|
6
|
What is the frequency of surveillance missions (per day / week / month /..)? What are their typical duration [...]
|
The SurvWebApp shall be compliant with the Performance Requirements defined in Section 11 of "Appendix [...]
|
20/08/2020
|
|
7
|
Will EMSA provide a predefined list of typical mission event to be selected by the users or all events [...]
|
The Mission Events shall be created/edited through a Mission Event Management Tool only by users with [...]
|
21/08/2020
|
|
8
|
Could you confirm whether EMSA or other stakeholders of the project will be involved in the management [...]
|
The Deployment Management shall be executed by users with Administration role only, as described in UC [...]
|
21/08/2020
|
|
9
|
• The main part of the solution we can provide for the improvement of the RPAS Exploitation Data Center [...]
|
According to “Annex B.02 Tender Specifications” section 4.2 EMSA requires the delivery of “Binaries of [...]
|
25/08/2020
|
|
10
|
• RPAS DC current software solution o What is there a current solution utilized to follow RPAS missions [...]
|
EMSA has currently in place a Service Contract for the provision of RPAS Exploitation Data Center services [...]
|
25/08/2020
|
|