11
|
According to the contract notice document, tenders will be opened on September 11. The exact time has[...]
|
Please refer to paragraph 3. of the invitation letter which states as follows: "3. Opening of the tenders[...]
|
09/09/2015
|
|
1
|
Clarification of the terms of the payment and instalments for the fulfilment of the contract, there is[...]
|
As mentioned in the draft contract (annex 5 to the technical specifications), there is no prefinancing[...]
|
22/07/2015
|
|
2
|
Could you please confirm that the duration of the project is 3 years/36 months?
|
We hereby confirm that the duration of the tasks is 3 years/36 months.
|
22/07/2015
|
|
3
|
Could you please confirm that the only evidence to be provided for the expert team is the detailed curriculum[...]
|
We hereby confirm that the only evidence to be provided for the expert team is the detailed curriculum[...]
|
18/08/2015
|
|
4
|
Could you please inform us of the indicative starting date of the contract?
|
We regret that we cannot provide you with an indicative starting date of the contract. After the deadline[...]
|
19/08/2015
|
|
8
|
Is it allowed to make a small modification in the heading of the Financial offer form (Annex 4) to enable[...]
|
Please do not make any modifications to the headings of the financial offer form (Annex 4).
|
03/09/2015
|
|
9
|
Page 11 of the Technical Specifications describes the requirements for the financial identification documentation[...]
|
No, for the supporting documents to the Financial Identification Form, please see footnote 5 of the form[...]
|
03/09/2015
|
|
7
|
The call seeks a coordinating organization that has to mobilize 90 NGOs to monitor the implementation[...]
|
Yes, but please provide details.
|
03/09/2015
|
|
10
|
The supporting documents for "Financial and economic capacity criteria and evidence" include: - "If applicable[...]
|
This condition is only applicable in cases where an indemnity insurance is required to cover special [...]
|
04/09/2015
|
|
5
|
We have a question related to the financial arrangements for the implementation of this project. We are[...]
|
We hereby confirm that in line with current practices, no prefinancing payment is envisaged for this [...]
|
20/08/2015
|
|