Call for tenders' details

Title:
Multiple FWC with Reopening of Competition for Architectural and Engineering Ser...
Contracting authority:
European Border and Coast Guard Agency (Frontex)
TED publication date:
28/12/2021
Time limit for receipt of tenders:
07/02/2022
Status:
Closed
Show filter parameters

Results per page: 10 | 25 | 50 24 Questions found, displaying 1 to 10.[First/Prev] 1, 2, 3 [Next/Last]
# Question Answer Last publication date Status
1
1. Please share Annex XI – Project reference contracts list
The Annex XI is published under Document library section - please check if the view option chose shows [...]
25/01/2022
2
2. Please share Annex XII – Technical Proposal Template
The Annex XII is published under Document library section - please check if the view option chose shows [...]
25/01/2022
3
12. Is realizing other contract for Frontex (2021) potential conflict of interest or not?
Realization of other contract for Frontex shall not be treated as a conflict of interests, however for [...]
27/01/2022
4
Proof B1 - Should the value of reference projects show our fee or the value of the project budget?
Evidence B1 shall show a combined total minimum value (project budget) of the three projects of 750,000.00 [...]
27/01/2022
5
Should we identify subcontractors cooperating with us under a BtoB agreement and having our company email [...]
If the Tenderer foresees subcontracting, then shall identify all subcontractors (and other entities not [...]
27/01/2022
6
Can the contract (document Contract_notice) be negotiated? There are statements in the submitted draft [...]
The submission of a tender implies the acceptance of all the terms and conditions set out in this invitation [...]
27/01/2022
7
3. Scope described in 3.2 is quite wide. Which a challenge to estimate unit price when in the same time [...]
Being aware that the potential scope is wide, the Annex IV Financial Offer template is limited to a few [...]
27/01/2022
8
4. Please confirm that Contractor chosen by Frontex will have access to full as-built documentation with [...]
The Contractor will be given access to complete building as-built documentation necessary to perform [...]
27/01/2022
9
5. Will the currency of the contract be PLN or EUR?
The Contract will be concluded in EUR but projects can also be invoiced in PLN using exchange mechanism [...]
27/01/2022
10
6. Does Frontex have a standard of documentation and design which you want to keep during Project planning [...]
Frontex is open for the Contractor's templates in this regard.
27/01/2022