Results per page: 10 | 25 | 50 20 Questions found, displaying 1 to 10.[First/Prev] 1, 2 [Next/Last]
# Question Answer Last publication date Status
20
I successfully uploaded our tender, confirmed on my Screen. The mentioned confirmation Email is so far [...]
After a tender is successfully submitted, the system will send automatic email notification to the email [...]
27/02/2018
19
In the RFQ there is nothing mentioned about provision of documents such as - Legal and Regulatory capacity [...]
The documents to be provided to justify the capacity of the tenderer are described in the section 2 of [...]
09/02/2018
18
Do we need 2 offers (financial and technical) to upload? Due to our company policy we have both in one [...]
The financial and technical offer can be provided in one document.
09/02/2018
17
At „Parties” => „Identification of the tenderer” => “Edit - Private company” => “Required fields [...]
The "Declaration on Honour on Exclusion and Selection criteria" could be uploaded only in "Required fields [...]
08/02/2018
16
In e-Submission: 1. At “Tender Data” part are two cells for fill: a. Total amount exclusive of taxes [...]
It is correct to put in “Total amount exclusive of taxes” the grand total (VAT excluded), while in “Total [...]
08/02/2018
15
On your announcement about "The tender deadline will be extended. The new deadline will become in force [...]
The Technical Specifications has been updated with the table detailing the requirements laid down in [...]
07/02/2018
14
May emission data from other Emission Measurement Systems (not compliant with 2017/1151) be offered here [...]
Yes, emission data from other Portable Emission Measurement Systems (not compliant with the Regulation [...]
07/02/2018
13
2017/1151 is much more than only the specifications of the PEMS system. It also includes how you calibrate [...]
For the purpose of this procurement procedure, the table detailing the requirements laid down in Regulation [...]
06/02/2018
12
Could you please confirm that the PEMS validation procedure is required as of described in Appendix 3 [...]
For the purpose of this procurement procedure, the table detailing the requirements laid down in Regulation [...]
06/02/2018
11
Could you please explain what to expect when a non-standard protocol test is requested. As it is only [...]
For the purpose of this procurement procedure, the table detailing the requirements laid down in Regulation [...]
06/02/2018