21
Can the same person covers the position of B1. Project Manager and the position of the expert B3.b as[...]
The minimum number of persons to fulfil the criteria B1 and B3 is one. There is no specific restriction[...]
08/05/2020
Answered
20
Can you please clarify whether the minimum number of 1000 replies collected from SMEs stated in section[...]
In accordance to point 1.7 of the technical specifications, one of the key performance indicators measured[...]
08/05/2020
Answered
19
In the work packages 3 and 4, startups are not explicitly listed as being in the scope of the research[...]
Yes. The scope of workpackages 3 and 4 should include support policies / delivery mechanisms for CSR [...]
08/05/2020
Answered
18
Can you please clarify the status of the guidance documents the Commission has published; Paragraph 3[...]
Both documents are publicly available at the following links: My Business and Human Rights: A guide to[...]
06/05/2020
Answered
17
Page 22 of the ToR requires detailed CVs to be up to 2 pages. Will CVs listing qualifications, past work[...]
The detailed CV should include the relevant educational and professional qualifications and should be[...]
04/05/2020
Answered
16
Dear Madam/Sir In the answer to question 9, you have pointed out the option of translation of surveys[...]
The translations of an SME panel questionnaire is provided by the Commission free of charge. The responses[...]
04/05/2020
Answered
15
Can you please confirm that evidence for selection criteria A1, A2, A4 and B4 will be provided only on[...]
The ToR clearly specifies in point 4.3.4. Technical and professional capacity criteria and evidence, [...]
28/04/2020
Answered
14
In the e-Submission portal, we understand that we will submit Annex 6 under technical offer section. [...]
Yes, please submit the Annex 6 – Technical tender form under section Technical Tender in eSubmission.
27/04/2020
Answered
13
Dear Sir/Madam, I have a question with regard to technical criteria A4. Terms of Reference state that[...]
Dear Madam/Sir, According to the technical specifications point 1.4.2. Geographical scope of the tasks[...]
24/04/2020
Answered
12
Could you please clarify if there are any specific conditions for a natural person that we subcontract[...]
Point 4.2 VERIFICATION OF NON-EXCLUSION of the Technical Specifications All tenderers (natural or legal[...]
24/04/2020
Answered