Call for tenders' details

Title:
Fostering Digitisation of Public Sector and Green Transition in Europe through t...
Contracting authority:
European Commission, DG for Communications Networks, Content and Technology (CON...
TED publication date:
23/05/2022
Time limit for receipt of tenders:
29/06/2022
Status:
Closed
Hide filter parameters
Filter parameters


Results per page: 10 | 25 | 50 11 Questions found, displaying 1 to 10.[First/Prev] 1, 2 [Next/Last]
# Question Answer Last publication date Status
11
In the technical and professional capacity section (3.2.3), criterion T1 states “At least 5 years’ experience [...]
Tenderer needs to present at least 1 project similar in scope and complexity completed in last three [...]
20/06/2022
10
Section 1.4.4.1 on General Deliverables mentions KPIs, a monitoring report/system as well as a "presentation [...]
Presentation of data from national websites is linked to activities from Task 1 (1.4.3.1) - Collection [...]
03/06/2022
9
Can you please confirm that balance sheets are only to be provided upon request?
Evidence of economic and financial capacity F1 does not need to be provided with the tender but may by [...]
03/06/2022
8
With regards to the clickable map referenced in footnote 10, it seems the link provided is not directing [...]
Under the page https://joinup.ec.europa.eu/collection/nifo-national-interoperability-framework-observatory [...]
01/06/2022
7
Can you clarify requirements for boot camps location? According to the tender specification 1.4.3.2 , [...]
The boot camps should be delivered in different places and to attempt to geographically follow requirements [...]
01/06/2022
6
The tender includes a task 5 with ad hoc services. Should the technical offer for Task 5 include a series [...]
Please see Question5
01/06/2022
5
The RfS, on page 7, mentions: 'In addition, the contractor maybe also conduct a number of supporting [...]
Task 5 has become obsolete and the reference to it should be disregarded.
31/05/2022
4
In section 1.4.3.3 there is an incomplete sentence: 'This inclusive approach the the expectation of citizens [...]
We apologise for this clerical error. The sentence should read: "This inclusive approach encompasses [...]
31/05/2022
3
Given the scale of this tender opportunity and to ensure equal opportunities for all tenderers, we would [...]
Unfortunately, due to operational reasons we are not in a position to extend the submission deadline.
30/05/2022
2
Can you clarify if each partner of the consortium needs to complete Annex 6 "Administrative identification [...]
Yes, each partner should complete the Administrative identification sheet.
30/05/2022