8
|
Based on the dynamic environment of the projects and many stakeholders involved, it is foreseeable that [...]
|
In the offer, the tenderer should respect the foreseen maximum duration of 24 months and plan the activities [...]
|
16/09/2019
|
|
16
|
Can the project value be accounted for all services provided within a large project?
|
Provided that we understood your question correctly, please note that regardless of the amount of your [...]
|
17/09/2019
|
|
6
|
Do sites with lindane production related contamination (dioxins, furanes) also need to be addressed?
|
Since the scope of the contract focuses on lindane and HCH, contamination with other substances should [...]
|
16/09/2019
|
|
17
|
If the work within the field(s) of experience has already been finished, but the overall project work [...]
|
References may not include ongoing projects. However, you can provide evidence that the work in question [...]
|
17/09/2019
|
|
10
|
Is it meant, that for each field of experience at least three reference projects must be provided, resulting [...]
|
Indeed, for each of the three fields of experience the tenderer has to provide three reference projects [...]
|
16/09/2019
|
|
12
|
Is it necessary to hand in CVs for a supporting expert team? Would a list of names and qualifications [...]
|
As stated in the tender specifications, the experience of the project team required under criterion B3 [...]
|
16/09/2019
|
|
11
|
Is it permissible that one reference project covers multiple fields of experience? In that case it would [...]
|
Yes.
|
16/09/2019
|
|
9
|
Is it permissible, by the regulations of the two projects (Lindanet, current tender ENV.D.1/ETU/2019/ [...]
|
A beneficiary funded by Interreg Europe in the context of LINDANET can receive assistance from the contractor [...]
|
16/09/2019
|
|
13
|
Is there a preference by the EU Commission in which timely manner the Tasks 1 and 2 should be executed [...]
|
The duration of the contract of 24 months will probably require parallel and independent execution of [...]
|
16/09/2019
|
|
14
|
It is stated that the contractor will provide assistance to public authorities, amongst other things, [...]
|
The tenderer can offer to assist public authorities with pilot tests, but can only perform services and [...]
|
16/09/2019
|
|