We would like to understand the measurement of ""each day of delay"". a) We interprete a day of delay [...]
a) The WKP1 shall be performed within 12 (twelve) months starting from the date on which the contract [...]
19/06/2019
Ingħatat Tweġiba
20
a) Could you please indicate the maximum number of Authorisation Tickets (Certificates) for the 50.000 [...]
CORRIGENDUM INSTEAD OF 'However, please refer also to point 1.2 Scalability Requirements within the table [...]
19/06/2019
Ingħatat Tweġiba
21
Could you please indicate the maximum number of Authorisation Tickets (Certificates) in case that the [...]
CORRIGENDUM: INSTEAD OF 'Annex I - Part 2: Technical Specifications does not define a maximum amount [...]
20/06/2019
Ingħatat Tweġiba
11
In Annex B to the Annex 1 - Part 1 to the contract: Administrative Annex: "21 AA / EA per year" is referenced [...]
In Annex I – Part 2 Technical Specifications, page 10, 2.2. Scalability requirements – Phase 2: 20 AAs [...]
19/06/2019
Ingħatat Tweġiba
12
Are there any restrictions for the selection of an Accredited PKI Auditor?
Compliance with the Certificate Policy has to be ensured. Please check the Certificate Policy (Annex [...]
19/06/2019
Ingħatat Tweġiba
13
Could you please indicate the duration of the meetings?
The duration of the meetings are not expected to last more than 1 (one) working day per face to face [...]
19/06/2019
Ingħatat Tweġiba
14
Is it correct to assume that the external EA or AA must satisfy the Certificate Policy (CP) requirements [...]
No, we do not consider that a correct assumption. The contractor will have to define the EU root CA’s [...]
19/06/2019
Ingħatat Tweġiba
22
a) Would you accept an offer that includes the number of 2.000.000 supported C-ITS stations per year [...]
Ad a) Even if your business model is not certificate based, you please still need to give an indication [...]
20/06/2019
Ingħatat Tweġiba
15
We can not find any requirements for a Service Level Agreement. Could you please indicate what availability [...]
The delivery of the deliverables shall be according to the time plan. In terms of operational availability [...]
19/06/2019
Ingħatat Tweġiba
18
Could we assume English as language for all relevant project communication and support issues?
Yes, as defined also in several parts of Annex I – Part 2: Technical Specifications, see in sections [...]
19/06/2019
Ingħatat Tweġiba