Information om udbud

Titel:
EU-rodcertificeringsmyndighed for samarbejdende intelligent transportsystem inkl...
Ordregivende myndighed:
European Commission, Joint Research Centre - Ispra (JRC-IPR)
Dato for offentliggørelse på Ted:
19/04/2019
Frist for modtagelse af bud:
07/08/2019
Status:
Lukket
Skjul filterindstillinger
Filterindstillinger


Results per page: 10 | 25 | 50 95 Spørgsmål found, displaying 26 to 50.[First/Prev] 1, 2, 3, 4 [Next/Last]
# Spørgsmål Svar Senest offentliggjort Status
49
Could you please explain the reason why C equals 5 for WKP2 of Phase 1 and equals 10 for WKP2 of Phase [...]
The constant C was considered to take into account the specific situation in WKP/phase. Please, see the [...]
20/06/2019
13
Could you please indicate the duration of the meetings?
The duration of the meetings are not expected to last more than 1 (one) working day per face to face [...]
19/06/2019
21
Could you please indicate the maximum number of Authorisation Tickets (Certificates) in case that the [...]
CORRIGENDUM: INSTEAD OF 'Annex I - Part 2: Technical Specifications does not define a maximum amount [...]
20/06/2019
31
Could you please provide the definition of "compliance assessment criteria"
Compliance/conformity assessment is to be interpreted as defined in the main part of the C-ITS Delegated [...]
20/06/2019
29
Could you please provide the number of 'of end-entities’ subscriber organisations?
This is not defined at this moment as it is based on market demand. It is foreseen that the Specific [...]
20/06/2019
30
Could you please provide the number of C-ITS station types?
This is not defined at this moment as it is based on market supply of C-ITS stations.
20/06/2019
27
Could you please provide the percentage breakdown of fixed and mobile C-ITS stations?
The percentage breakdown is not defined at this moment as it will depend on the market demand. It is [...]
20/06/2019
4
Dear Sirs, Please indicate the section of the Call from tender from where we could download the following [...]
The tender documents will be published as soon as possible. The deadline for submission of tenders will [...]
19/06/2019
1
Dear, Could you make the documents available for download, as I can only see the Invitation Letter? Kind [...]
The tender documents will be published as soon as possible. The deadline for submission of tenders will [...]
19/06/2019
35
Following is written in clause II.6.3: The contractor is liable for any loss or damage caused to the [...]
With reference to Article II.6.3. we confirm that the "total amount of the contract" does refer to the [...]
20/06/2019
91
From the answer to Question 90 we assume that a new deadline will be defined for the tender. Since tender [...]
The deadline will be postponed, The postponement will be published in a corrigendum of the e notice, [...]
19/07/2019
3
Good day, where can I download the tender specification of the above mentioned tender? Thank you.
The tender documents will be published as soon as possible. The deadline for submission of tenders will [...]
19/06/2019
8
I don't find the documents and the tender specifications with their respective annexes, where I can find [...]
The tender documents will be published as soon as possible. The deadline for submission of tenders will [...]
19/06/2019
11
In Annex B to the Annex 1 - Part 1 to the contract: Administrative Annex: "21 AA / EA per year" is referenced [...]
In Annex I – Part 2 Technical Specifications, page 10, 2.2. Scalability requirements – Phase 2: 20 AAs [...]
19/06/2019
24
In document "EN-05 Annex I Part 2 Technical Specifications", chapter "2.2. Scalability requirements", [...]
For the purpose of Phase 2 in the evaluation table, the number of 21 is only indicative to provide an [...]
20/06/2019
76
In order to be compliant to point 8 from Annex 3 “Compliance Audit And Other Assessments” and in particular [...]
The Certificate Policy, which is [1] of Annex I to the Contract - Part 2: Technical Specifications, defines [...]
09/07/2019
74
In order to follow all the requirements specified in the Tender Documentation is possible to Have a specific [...]
We do not see a need for an additional communication network to be setup between the different environments [...]
09/07/2019
43
IN ORDER TO SUBMIT A COMPETITIVE FINANCIAL AND TECHNICAL OFFER AND TO PRODUCE ALL DECLARATIONS REQUESTED [...]
Kindly note that a corrigendum of official journal will be published soon.
20/06/2019
77
In reference to the policy document cellar_9a2fe08f-4580-11e9-a8ed-01aa75ed71a1.0005.02_DOC_4.pdf, we [...]
The three mentioned environments should be fully separated, we do not see a way to centrally manage log [...]
09/07/2019
38
In relazione alla procedura di cui in oggetto ed al termine ultimo fissato per la presentazione della [...]
Vi informiamo cha a breve sarà pubblicata la rettifica della Gazzetta ufficiale.
20/06/2019
23
In terms of "interacting with the Accredited Auditors" can the JRC clarify whether CA compliance audits [...]
We confirm that the contractor will be responsible for the entire process of auditing the EU Root CA, [...]
20/06/2019
6
In the Document Library only the Invitation letter is available, do you expect to upload the Tender specifications [...]
The tender documents will be published as soon as possible. The deadline for submission of tenders will [...]
19/06/2019
80
In the EN-04 Financial offer Evaluation table, more exactly in the row 25, Base services provision, is [...]
The second phase of the contract is regulated by a framework contract, and services will be ordered by [...]
11/07/2019
87
In the Evaluation table row 25, could you please indicate which costs should the provider insert?
The base service provisions include the costs for the support for the EU Root CA, internal EA and AA [...]
16/07/2019
14
Is it correct to assume that the external EA or AA must satisfy the Certificate Policy (CP) requirements [...]
No, we do not consider that a correct assumption. The contractor will have to define the EU root CA’s [...]
19/06/2019