1
|
With regard to selection criterion 1, must a similar service provision necessarily and directly be related [...]
|
The provision of three ‘similar services’ must, in order to meet selection criterion 1, always be linked [...]
|
09/08/2019
|
|
2
|
With regard to selection criterion 2, how do you assess the "confirmed" character of the minimum experience [...]
|
Yes, this minimum experience must be in the field of accessibility to buildings.
|
09/08/2019
|
|
3
|
Concerning selection criterion 3, is it required that the two requested texts have been published in [...]
|
Both possibilities mentioned would be accepted, provided that they are intended for a general public [...]
|
09/08/2019
|
|
4
|
Can you specify the following clause? “The European Parliament reserves the right to exercise the option [...]
|
The European Parliament may use a negotiated procedure without prior publication of a contract notice [...]
|
09/08/2019
|
|
5
|
It is stated on page 6 of the administrative provisions that the fixed price includes travel and subsistence [...]
|
Only for the start-up meeting of the framework contract (with each contractor), will the travel expenses [...]
|
09/08/2019
|
|
6
|
The contract provides for three "cascade" framework contracts to be signed. Will the second and third [...]
|
No, the contractors ranked 2nd and 3rd will not be informed of the general activity of the contractor [...]
|
09/08/2019
|
|
7
|
On page 5 of the technical specifications, "audits previously carried out" are mentioned. Will the evaluation [...]
|
Tenders are evaluated exclusively on the basis of the award criteria described on pages 16 and 17 of [...]
|
09/08/2019
|
|
8
|
How do you assess whether price P could be evaluated as abnormally low, and that it does not distort [...]
|
The analysis of a price considered as abnormally low would be carried out in accordance with the principles [...]
|
09/08/2019
|
|
9
|
Page 8 of the technical specifications. Does an active or passive refusal - or repeated refusal - by [...]
|
No. The contractor may be unable to perform the services without this resulting in the termination of [...]
|
09/08/2019
|
|
10
|
Page 8 of the technical specifications. Do the contractors ranked second and third have to adapt themselves [...]
|
No, if the contractor ranked 1st is unable to perform the services, the contractor ranked 2nd will perform [...]
|
09/08/2019
|
|