# Otázka Odpověď Datum posledního zveřejnění Stav
25
We notice that there is a standard formulation that the project is free of taxes. It is our experience [...]
The Consultant might be exempt from direct and indirect taxes in the countries where it will have to [...]
04/11/2019
26
For purpose of tax calculation, kindly provide us with information on: 1 the time expressed in months [...]
Please refer to the preceding answers.Question25
04/11/2019
27
Please clarify the deadline of the proposal's submission. (The eTendering indicates as deadline: 12/11 [...]
The deadline for submitting the offers is the 15th of November 2019, 23:59 CET. A corrigendum will be [...]
04/11/2019
28
The Instructions to tenders indicate the deadline for submission of tenders to be 15/11/2019, whereas [...]
The deadline for submitting the offers is the 15th of November 2019, 23:59 CET. A corrigendum will be [...]
04/11/2019
29
We note that there is the provision in the contract for pre-financing, with the requirement for a pre-financing [...]
The template is provided on the Document Library under the name: “Declarations and other Templates - [...]
04/11/2019
30
Could you please clarify if South Africa is included in the project? The contract notice excludes South [...]
Yes, the Contracting Authority confirms that South Africa is excluded from the scope of this programme [...]
04/11/2019
31
Our consortium notes, pursuant to information contained in the TOR, that the tax and customs arrangements [...]
The Consultant might be exempt from direct & indirect taxes (e.g. VAT, income tax) in the countries [...]
04/11/2019
32
In the Instructions to tender it is stated that "Deadline for receipt of tenders by the Contracting Authority [...]
The deadline for submitting the offers is the 15th of November 2019, 23:59 CET. A corrigendum will be [...]
04/11/2019
33
On the TED platform the Project name is given as "Technical Assistance Facility for the Clean Ocean Initiative [...]
While both names can be referred to, we suggest to use the following name: The Clean Oceans Initiative [...]
04/11/2019
34
Refering to AA-010039-001 TAINSTRUCT 5.3 "The Reference period which will be taken into account will [...]
The Contracting Authority confirms that the reference period for the project presented as references [...]
04/11/2019
35
Ref ToR § 6.6 p19: we understand that the implementation of the 5 pilot projects will be financed by [...]
Yes the cost for implementation of the pilot projects shall be covered under the incidental costs. The [...]
04/11/2019
36
Reference to TAINSTRUCT Chapter 22 and Annex 9: Usually foreign companies must register in the project [...]
The Consultant might be exempt from direct and indirect taxes in the countries where it will have to [...]
04/11/2019
37
The EIB will propose 5 potential project ideas. 1/ In which countries would these projects be located [...]
The contracting Authority confirms that this information is not available at this stage and will be communicated [...]
04/11/2019
38
Please provide the list of countries and cities, where EIB has regional representation
This information is available from EIB web site (https://www.eib.org/en/infocentre/contact/offices/index.htm [...]
04/11/2019
39
CVs for non-key experts are not requested and will not be evaluated. How do you expect the Tenderer to [...]
Information pertaining to the access to non-key experts will be evaluated as part of the Organisation [...]
04/11/2019
40
The Tender provides a budget and the number of projects to be delivered by the consultant at each stage [...]
The bidders will have to explain in their methodology how they intend to scope the projects so that they [...]
04/11/2019
41
Projects being effective regarding Clean Oceans are expected to have a significant size and may also [...]
Possible types of surveys are indicated in the Terms of Reference section 4.2.3. As stated, the costs [...]
04/11/2019
42
The Annex V : BUDGET indicates clearly the number of projects: - 20 projects identified - 10 projects [...]
The consultant may identify and propose more than the minimum number of projects at each stage allowing [...]
04/11/2019
43
Ref ToR § 6.3 page 18: Are the key experts (in particular the KE1 Team leader), and the non key experts [...]
Please refer to the Terms of Reference, Section 6.1 which states: “Each of the key experts are allowed [...]
04/11/2019
44
Can we assume that (selected) project will not be situated in high risk countries and/or regions? If [...]
Projects should be selected in locations and countries where the likelihood for successful preparation [...]
04/11/2019
45
Can you confirm that the fields in which (at least 20 of) the permanent staff of the tenderer are required [...]
The Contracting Authority confirms that the permanent staff of the tenderer are required to work are: [...]
04/11/2019
46
Can you please specify the reference period (since reference is made to ‘the last three years from submission [...]
The Contracting Authority confirms that the reference period for the project presented as references [...]
04/11/2019
47
Ref to ToR 6.1: “Each of the key experts are allowed to spend a maximum of 30% of their time allocated [...]
It is the responsibility of the Consultant to provide suitable working conditions to its staff for the [...]
04/11/2019
48
Can you confirm that only one original Technical offer and Financial offer have to be submitted?
The Technical offers and the financial offers must be submitted in separate envelopes (double envelope [...]
04/11/2019
49
Can you please indicate what you do consider as “The electronic version of the technical offer” that [...]
The Technical offers and the financial offers must be submitted in separate envelopes (double envelope [...]
04/11/2019