# Spørgsmål Svar Senest offentliggjort Status
40
Your former answer to question nr.38 appears to be contradictory to what is stated in Annex II of the [...]
For case study 2, only plane/tickets to the hosting city and back. For case study 3, “collective round-trip [...]
12/06/2019
33
You request in Award Criterion 1, our approach towards timely reporting but there is no official mention [...]
Please refer to section 1.3 “Implementation of the Framework Contract”, to the last paragraph: “After [...]
03/06/2019
12
What is the annual proportion between events in Belgium, events in Europe and events outside of Europe [...]
Framework contracts stipulate the subject matter of the purchase, the price list, the parties, the legal [...]
22/05/2019
29
We understand that a unique management fee applies per event, based on its location. However, you have [...]
The management fee for organisation of events to prepare, coordinate, find/book venues, etc. is a flat [...]
29/05/2019
27
We have well noted a budget line for the delivery of a registration website. There is however no indication [...]
The Contracting authority considers that, as the participants register themselves on the website, the [...]
29/05/2019
22
We have noticed that no percentage of total cost is applied to this budget line. Could you clarify if [...]
The price of a venue with equipment included is on real cost base. No margin should be applied.
29/05/2019
23
We have noticed that no percentage of total cost is applied to this budget line. Could you clarify if [...]
The accommodation allowing big sized dogs will be on a real cost base as it is considered the same as [...]
29/05/2019
20
we believe it is not possible to have a local network of own or identified providers in each EU country [...]
If the Contracting authority requests the presence of the event coordinator or any other profile as defined [...]
28/05/2019
24
There is no unit applied to this budget line. Should we consider it to be "real price + % of total price [...]
Price per Unit per day. Corrigendum of the price list will follow.
29/05/2019
59
there are 2 cells, we do not know how to proceed to encode. Please adivse. if "Real cost": shall we put [...]
In the list of prices, in the column “Unit”, when it says real cost, you shall not indicate anything [...]
20/06/2019
64
the price of this item is supposed to be at "real price". please indicate the amount to be completed [...]
Please refer to answer 59.
20/06/2019
63
the answer to question 13 is: "Could you please clarify why the contractor would send its staff and which [...]
The contracting authority does not foresee the presence of the contractor’s staff during an event. The [...]
20/06/2019
41
Thank you for your prompt reply, nevertheless, there is still some room for clarification. Please can [...]
A) Please refer to section 4 “contract award criteria”, criterion 1, which refers to the elements of [...]
12/06/2019
4
Regarding the following: '15 meters long zig zag exhibition with 15 photos with description plate for [...]
The text on the plate shall be provided by the Contracting Authority, while the plate itself shall be [...]
17/05/2019
3
Regarding the following: '- 1 stand to be installed in a building of the contracting authority dimensions [...]
The storage surface is included in the 30 sqm.
17/05/2019
8
Regarding the first 3 lines, i.e. the following: 'Management fee for organisation of event to prepare [...]
Your understanding is correct.
17/05/2019
17
Regarding an Open Day Event with 1000 participants, How do we invoice this event, as the management fee [...]
Management fees for organisation of event to prepare, coordinate, find/book venues, etc. are applicable [...]
22/05/2019
35
Please could you indicate in the NEW document the new/changed parts in both documents instead of us checking [...]
• In the technical specifications, the first paragraph of section 1.1 and first paragraph of section [...]
04/06/2019
43
please confirm there is no translation services to be foreseen. thank you.
No translation foreseen in case study 1, 2, 3.
13/06/2019
44
please confirm there are no interpretation services to be foreseen. Meetings on case study 2 and case [...]
For case study 2, 2 sign language interpreters (from English) are required. For case study 3, no interpretation [...]
13/06/2019
62
please confirm the value to be indicated since the price is "Reimbursed according to EC mission guide [...]
The bidder shall not fill in the unit price as it will be reimbursed according to EC mission guide.
20/06/2019
47
please confirm that no photographer has to foreseen in any of the three case study since it is not stated [...]
Please refer to case study 1, “services to be provided”. A photographer is requested for the whole day [...]
13/06/2019
39
P.22 of the ToR states that the price of the tender is a combination of the estimates for the three case [...]
As stated on page 1 of annex II “Case studies”, “For the award of the contract, the tenderer shall, as [...]
07/06/2019
14
Our understanding is that there is no difference of flat fee between the different types of events. The [...]
Your understanding is correct.
22/05/2019
15
Our understanding is that the same fee is applicable for an event with 50-70 and an event with 10 participants [...]
Question14