40
Can you please clarify section 4.3. A. Quality criteria, which says: “For each criterion, the general[...]
- the weight of the “general description of the approach, organisation, methods and tools” is 30%. - [...]
20/02/2019
Beantwortet
39
For the requirement that “out of the 10 minimum references, the list shall include at least two audits[...]
Please refer to the Criteria relating to tenderers: “The tender must contain a description of the tenderer's[...]
18/02/2019
Beantwortet
38
With reference to your answer to Question 2, which referred to whether the DGs will accept examples where[...]
Yes we confirm.
18/02/2019
Beantwortet
37
We are coming back to your reply to Q&A #19: We would appreciate if you could provide an amended [...]
We will upload the amended version of the Declaration on Honour.
18/02/2019
Beantwortet
36
On page 30 of the Tender Specification It says “The tenderers initially shall not provide any other evidence[...]
“The tenderers initially shall not provide any other evidence for compliance with the selection criteria[...]
14/02/2019
Beantwortet
35
According to the draft request for services (shared management), p.70, the auditor should use the checklists[...]
The checklist depends on the Fund to be audited, there is no standard common checklist. For the shared[...]
13/02/2019
Beantwortet
34
Could you please clarify the meaning of the sentence ‘Batch assignments under shared management mode [...]
For Shared Management mode, without prejudice to what is agreed in specific terms of reference and generally[...]
13/02/2019
Beantwortet
33
On page 29 of the tender specifications it is stated that “all subcontractors whose share of the contract[...]
We confirm that only subcontractors whose share of the contract is above 20% and/or whose capacity is[...]
07/02/2019
Beantwortet
32
According to the Tender Specifications, not only the prices per category (Annex 3) but also the prices[...]
The price schedule refers to the daily rate per profile that the contractor will be allowed to charge[...]
07/02/2019
Beantwortet
31
On page 9 of the tender specifications it is stated “tenders must be presented as follows: Part A: Identification[...]
The bidder should upload the documents in each of the corresponding part of the portal on the basis of[...]
07/02/2019
Beantwortet