1
|
Dear Sirs, Will the technical and logistical support requested by Call for Tenders N° HOME/2018/ISFP/ [...]
|
As stated, in Point 2.1 of the technical specifications, “the contracting authority intends to conclude [...]
|
07/05/2019
|
|
2
|
Dear sirs, Can the contracting authority confirm that this contract will not be used to deliver RAN and [...]
|
Your question does not relate to the Technical specifications of this Call for tender. We refer to the [...]
|
08/05/2019
|
|
3
|
Regarding the following: '- 1 stand to be installed in a building of the contracting authority dimensions [...]
|
The storage surface is included in the 30 sqm.
|
17/05/2019
|
|
4
|
Regarding the following: '15 meters long zig zag exhibition with 15 photos with description plate for [...]
|
The text on the plate shall be provided by the Contracting Authority, while the plate itself shall be [...]
|
17/05/2019
|
|
5
|
Concerning the Slido wall, are we allowed to propose other interactive tools?
|
No, only Slido in order to allow the comparison of offers and guarantee a fair and equal treatment.
|
17/05/2019
|
|
6
|
Is it possible to provide the key messages that need to be conveyed by the stand?
|
This is not requested for the case study. If provided in the offer it will not be considered at the evaluation [...]
|
17/05/2019
|
|
7
|
Except the graphic guidelines from the European Commission, is there any visual identity that needs to [...]
|
No, only the graphic guidelines from the European Commission need to be followed for the case study.
|
17/05/2019
|
|
8
|
Regarding the first 3 lines, i.e. the following: 'Management fee for organisation of event to prepare [...]
|
Your understanding is correct.
|
17/05/2019
|
|
9
|
Could you please specifiy what is required for the case studies? Just the "services to be provided" as [...]
|
The general part of the technical offer shall focus on a description of how the tenderer intends to implement [...]
|
17/05/2019
|
|
10
|
In the Call for Tenders, page 18, in the section A. Criteria relating to Tenderers, it is mentioned that [...]
|
1) Projects listed as evidence under criteria A1 should have been carried out within the past 5 years [...]
|
22/05/2019
|
|
11
|
Could you please indicate the budget allocation between Framework contrat prices and reimbursables ?
|
Framework contracts stipulate the subject matter of the purchase, the price list, the parties, the legal [...]
|
22/05/2019
|
|
12
|
What is the annual proportion between events in Belgium, events in Europe and events outside of Europe [...]
|
Framework contracts stipulate the subject matter of the purchase, the price list, the parties, the legal [...]
|
22/05/2019
|
|
13
|
Does this management fee outside of Belgium include transport and accommodation costs for the Contractor's [...]
|
Could you please clarify why the contractor would send its staff and which staff profile ?
|
22/05/2019
|
|
14
|
Our understanding is that there is no difference of flat fee between the different types of events. The [...]
|
Your understanding is correct.
|
22/05/2019
|
|
15
|
Our understanding is that the same fee is applicable for an event with 50-70 and an event with 10 participants [...]
|
Question14
|
22/05/2019
|
|
16
|
Our understanding is that the same fee is applicable for all types of events. Is it correct ?
|
The management fee is a flat rate and varies only depending on the location where the event takes place [...]
|
22/05/2019
|
|
17
|
Regarding an Open Day Event with 1000 participants, How do we invoice this event, as the management fee [...]
|
Management fees for organisation of event to prepare, coordinate, find/book venues, etc. are applicable [...]
|
22/05/2019
|
|
18
|
Could you please clarify the expertise/domains required for trainers and coaches both for the “general [...]
|
Trainer/coach shall be understood as a professional used during team building activities. In the case [...]
|
28/05/2019
|
|
19
|
can we consider that the stand will be located in the same area than during the OpenDays in 2019?
|
The location is in Brussels and the venue is provided in the case study by the Commission at zero cost [...]
|
28/05/2019
|
|
20
|
we believe it is not possible to have a local network of own or identified providers in each EU country [...]
|
If the Contracting authority requests the presence of the event coordinator or any other profile as defined [...]
|
28/05/2019
|
|
21
|
Given the presence of several other specific event focused tenders and a natural limit in business development [...]
|
The Contracting Authority does not foresee extending the deadline for submission.
|
29/05/2019
|
|
22
|
We have noticed that no percentage of total cost is applied to this budget line. Could you clarify if [...]
|
The price of a venue with equipment included is on real cost base. No margin should be applied.
|
29/05/2019
|
|
23
|
We have noticed that no percentage of total cost is applied to this budget line. Could you clarify if [...]
|
The accommodation allowing big sized dogs will be on a real cost base as it is considered the same as [...]
|
29/05/2019
|
|
24
|
There is no unit applied to this budget line. Should we consider it to be "real price + % of total price [...]
|
Price per Unit per day. Corrigendum of the price list will follow.
|
29/05/2019
|
|
25
|
Are you expecting tenderers to propose a percentage at this bidding phase or is this to be specified [...]
|
The Contracting authority expects the bidder to indicate the percentage at this bidding phase. The percentage [...]
|
29/05/2019
|
|