10
|
I.5.2 states that interim payments are not applicable to the contract. However with the 13 month duration [...]
|
An advance payment is foreseen upon signature of the contract by both parties, amounting to 30% and therefore [...]
|
01/07/2020
|
|
9
|
When you write "... provide references for projects delivered (...) in the last three year", do you mean [...]
|
If the project was on-going during the last three years it is acceptable as a reference, since the required [...]
|
29/06/2020
|
|
8
|
Reference projects for criteria A1, A2 and A4 must have a minimum value of EUR 500.000 and have been [...]
|
The contracts have to be partially or totally carried out in the period of time referred to – the threshold [...]
|
29/06/2020
|
|
7
|
As a UK based company, are we allowed to participate in partnership with a company based in one of the [...]
|
Yes, since we have published the tender and will even issue the contract within the transition period [...]
|
29/06/2020
|
|
6
|
In the tender specification section 4.2, the criteria sought includes “experience in the field of ….with [...]
|
In section 4.2, all Evidence refers to the specific Criterion Therefore, with regard to Criterion A.1 [...]
|
25/06/2020
|
|
5
|
Can you kindly clarify in section 4.2.4, if the expert with 3 years’ professional experience in legal [...]
|
Criterion A3 requires “Experience in the legal and regulatory framework for rail in the EU, in particular [...]
|
25/06/2020
|
|
4
|
CHANGE OF DEADLINE: We are very keen to participate in the forthcoming tender for the above-mentioned [...]
|
We acknowledge that the minimum deadline was given and are prepared to extend the deadline. The new deadline [...]
|
25/06/2020
|
|
3
|
The specification states that the contract duration is one year during 2021, to be followed by a 7 year [...]
|
This procurement procedure being awarded for 2021 is for the award of a follow up contract to the services [...]
|
25/06/2020
|
|
2
|
Can you confirm or otherwise if the successful bidder for the subject contract will be eligible to bid [...]
|
This procurement procedure is being awarded for 2021 for the award of a follow up contract to the services [...]
|
25/06/2020
|
|
1
|
The selection criteria mentions that the tenderer must prove 5-years of experience on ERTMS projects [...]
|
Considering the priority of having ERTMS deployed in EU Countries, and the exact wording specified in [...]
|
24/06/2020
|
|