Details zur Ausschreibung

Titel:
Unterstützung bei der Bewertung der Pläne und Umsetzung der Wasserrahmenrichtlin...
Öffentlicher Auftraggeber:
European Commission, DG ENV+CLIMA
Datum der Veröffentlichung im TED:
09/07/2015
Frist für den Eingang von Angeboten:
11/09/2015
Status:
Geschlossen
Filter-Parameter ausblenden
Filter-Parameter


Results per page: 10 | 25 | 50 12 Fragen found, displaying 1 to 10.[First/Prev] 1, 2 [Next/Last]
# Frage Antwort Datum der letzten Veröffentlichung Status
12
Will the source code of the IT tool developed for the assessment of the 1st RBMPs be made available at [...]
Yes
03/09/2015
11
Are there documents related with the IT tool developed for the assessment of the 1st RBMPs available? [...]
The 2 documents that were recently uploaded are concerning the IT tool developed for the assessment of [...]
02/09/2015
10
Regarding the experience required for the Project Manager(PM) of the team delivering the service, we [...]
Yes, this is correct.
31/08/2015
9
1. Could be the tender be specific for one watershed or may include all the watersheds from the Member [...]
1. The evaluation of the 2nd RBMPs should cover all river basin districts of all Member States. Only [...]
04/08/2015
8
Can the European Commission please confirm it agrees on the additional wording as inserted in speech [...]
DG Environment is using the standard service contract in use for procurement contracts in the Euroean [...]
29/07/2015
7
Can the European Commission please confirm if an exclusion of consequential damages can be added to Clause [...]
The contractor is liable for any loss or damage sustained by the contracting authority during or as a [...]
28/07/2015
6
Regarding Clause II.12, the liability for liquidated damages is unlimited which is not in line with the [...]
The liquidated damages which cover the delay in the execution (or correct execution) of the obligation [...]
28/07/2015
5
Clause II.1.1 of the contract conditions requires a performance by the consultant to the highest professional [...]
The contractor must provide services that meet the highest quality standards, in accordance with the [...]
28/07/2015
4
Regarding Clause I.4, please confirm all payments by the European Commission under this contract shall [...]
Payments will be made within 60 days of receipt of invoices in accordance with Article 13 of the above-mentioned [...]
28/07/2015
3
Would the European Commission accept an alternative payment profile to Article I.4 based on our proposed [...]
The payment schedule has been calculated according to the expected timeline of the project. A payment [...]
28/07/2015